Rs 36,000 cr worth of power projects stuck for coal

HT Correspondent, Hindustan Times  New Delhi, July 24, 2014
First Published: 23:58 IST(24/7/2014) | Last Updated: 00:00 IST(25/7/2014)

Power projects worth around Rs. 36,150 crore and a generation capacity of 7,230 MW are stranded due to coal shortage, Piyush Goyal, minister for coal, power and renewable energy, said in the Lok Sabha on Thursday.

“As far as coal-based thermal power plants are concerned, a capacity of 7,230 MW is already commissioned but having no coal supply. Considering an indicative cost of Rs. 5 crore per MW, an investment of about Rs. 36,150 crore has been made in the execution of these projects,” Goyal said in a written reply to a question in the lower house.

This 7,230 MW capacity is spread across 12 projects.

To address the issue of coal shortages, the power ministry has initiated certain steps including issuance of advisory to import the fuel.

As per the advisory, the cost of imported coal would be made a pass through on case to case basis by regulators to the extent of shortfall in the quantity indicated in the LoA (letter of assurance) or fuel supply agreement (FSA).
 
In a separate reply, Goyal said the government is “making efforts to make adequate fuel available for power generation through coal companies”


Advertisement
more from Business

Tata, Singapore Air venture Vistara to take off on January 9

Based in New Delhi, the full service Vistara will begin operations with a fleet of new Airbus A320-200s with 148 seats, Tata SIA Airlines Ltd said in a statement. Vistara will offer flights to Mumbai and Ahmedabad initially.
markets
Advertisement
Most Popular
Advertisement
Advertisement
Copyright © 2014 HT Media Limited. All Rights Reserved