NTPC's 6th unit bunker collapses in Bihar

PTI  Bhagalpur , April 15, 2012
First Published: 19:08 IST(15/4/2012) | Last Updated: 19:38 IST(15/4/2012)

The bunker of the 6th unit of the NTPC thermal power plant at Kahalgaon in Bhagalpur district on Sunday collapsed halting power generation from the unit with 500 MW capacity, an official said.

Advertisement

The bunker used for storage of coal for combustion in boiler furnace collapsed following technical snag forcing suspension of power generation, NTPC Kahalgaon unit General Manager Subhashi Ghosh said.

A team of technical experts from New Delhi would come to Bhagalpur on Monday to restore the bunker, he said.

Meanwhile, power generation from the NTPC thermal power plant has plummeted to 1340 MW out of its total capacity of 2340 MW with the seventh unit with generation capacity of 500 MW already out of order for some time, Ghosh said.

Efforts were on to resume generation from the seventh unit at the earliest, Ghosh said.


Advertisement
more from India

Rahul targets Modi, Sena over price rise,‘bullying’

Congress vice-president Rahul Gandhi on Friday targeted Prime Minister Narendra Modi and his government on the rising prices of vegetables, saying ‘tall promises’ had been made to people but there was a huge difference between one’s words and the deeds performed.
Advertisement
Most Popular
Advertisement
Advertisement
Copyright © 2014 HT Media Limited. All Rights Reserved