New Elphinstone flyover hits speed bump

Published on: Oct 02, 2025 06:30 am IST

The Indian Railways has raised a red flag, warning it won’t allow the project to proceed until its demand for “way leave charges” is approved

MUMBAI: The clock has begun ticking on rebuilding the Elphinstone road-overbridge (ROB), one of Mumbai’s most complex infrastructure projects. But before the project actually gets underway, the Indian Railways has raised a red flag, warning it won’t allow the project to proceed until its demand for “way leave charges” is approved.

Mumbai, India. Sep 15, 2025 - Mumbai Metropolitan Region Development Authority (MMRDA) started demolishing the Elphinstone Bridge after it was closed for traffic. MMRDA will construct a new Elphinstone Bridge along with the Seree-Worli Connector. Mumbai, India. Sep 15, 2025. (Photo by Raju Shinde/HT Photo) (Raju Shinde)
Mumbai, India. Sep 15, 2025 - Mumbai Metropolitan Region Development Authority (MMRDA) started demolishing the Elphinstone Bridge after it was closed for traffic. MMRDA will construct a new Elphinstone Bridge along with the Seree-Worli Connector. Mumbai, India. Sep 15, 2025. (Photo by Raju Shinde/HT Photo) (Raju Shinde)

The bridge, a vital east-west connector between Prabhadevi and Parel, straddles sections of the Western and Central railways, both suburban railways in Mumbai. This means Maha Rail (Maharashtra Rail Infrastructure Development Corporation), which is executing the project, will need to use railway land to construct the new state-of-the-art, double-deck flyover. For this, the railways are due “way leave charges” – effectively rent – for the project’s estimated two-year duration.

While the Central Railway (CR) is asking for 10 crore, the Western Railway (WR) has asked Maha Rail to cough up 59.14 crore, a sum yet to be approved by the Mumbai Metropolitan Region Development Authority (MMRDA), which has contracted the project to Maha Rail, a joint venture between the state government and the Indian Railways.

Preliminary work on demolishing the Elphinstone ROB, also called Carrol bridge, began on September 10. The asphalt has been ripped up on the approach roads at both ends of the bridge, and paver blocks on the footpaths too have been torn up. However, the railways have not allowed the section of the bridge above the railway tracks to be demolished until their demand is met. The 167-crore project already finds itself wrapped in red tape, slowing its progress.

Senior railway officials said that when permission for the project was sought from the railways in mid-2022, the CR responded to Maha Rail, asking for 10 crore as way leave charges.

It wasn’t quite as simple for the WR. Officials from the railway say they received Maha Rail’s letter on the project a few days after the CR had received theirs. In the interim, they say, the Railway Board had amended certain rules, which considerably raised the way leave charges due to them.

While WR has asked for 59.14 crore, Maha Rail released 9 crore, but the railway returned the money, insisting that the full sum be deposited before it clears the way for the project to proceed.

“We are demanding 36.11 crore as way leave charges and 23.03 crore as other departmental fees. In contrast, the Central Railway had asked for 10 crore only, and they gave approval after 5 crore was deposited,” said a railway official.

Maha Rail questions why different railway zones in the same city are charging different fees. “The total project cost is 167 crore and the railways are asking for more than 60 crore for these approvals. We have met with MMRDA on the issue as they will foot the bill,” said a Maha Rail official. MMRDA did not respond to requests for a comment.

The Western Railway is also miffed with Maha Rail for its delay in responding to queries relating to technical details about the new ROB. The section of the bridge that falls under railway jurisdiction is 132 metres. In March, the WR had suggested that the implementation agency make certain technical changes but this took six months to resolve.

Meanwhile, construction of the new bridge has impacted two buildings flanking the proposed structure – Laxmi Nivas and Haji Noorani Chawl. Both buildings will be demolished and the 83 families living in them relocated to new homes. Under a MHADA-MMRDA agreement, these families will receive permanent housing.

MHADA has identified 119 apartments in areas like Dadar, Matunga, Parel, Lalbaug, Sewri and Prabhadevi for these project-affected residents. These flats will be handed over to MMRDA in the next 15 days, after which the families will receive their keys.

The flats were acquired from private builders and are now being sold to MMRDA at 110% of the Ready Reckoner rate. The total deal is worth 129 crore.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
SHARE
close
Story Saved
Live Score
Saved Articles
Following
My Reads
Sign out
Get App
crown-icon
Subscribe Now!
AI Summary AI Summary

Indian Railways demands high "way leave charges" from Maha Rail for Elphinstone flyover project, delaying reconstruction. Western Railway seeks 59.14 crore, while Central Railway asks 10 crore. Project cost is 167 crore, with 83 families to be relocated.