Set to miss emission norm deadline, Panipat power plant yet to start work to curb pollution

Set to miss the December 2019 deadline to meet new emission norms, the Panipat Thermal Power Station (PTPS) in Haryana is yet to award a contract to install modern equipment to cut down on pollution, according to officials.
The Central Pollution Control Board (CPCB) had on November 13 issued a show-cause notice to the PTPS, warning that its unit 7 could be shut down for failing to meet the year-end deadline to cut down emissions of particulate matter (PM10), sulphur dioxide (SO2) and oxides of nitrogen (NOx).
It had given 15 days to the power station to file a reply.
Though the power plant management is yet to respond to the show-cause notice, it is likely to seek some more time to reduce pollution.
RE-TENDERING
IN PROGRESS
The Haryana Power Generation Corporation Limited (HPGCL), which operates the plant, is still to award a contract to install modern flue-gas desulphurisation (FGD) units, which cut emissions of sulphur dioxide, in unit 7.
Asked if they would be able to meet the deadline, Mohammed Shayin, the managing director of HPGCL, said, “We had floated tenders to install FGD units, but those who responded quoted abnormally high rates. So, nothing has been finalised yet. We have initiated the re-tendering process.” When the HPGCL consulted the National Thermal Power Corporation Limited on the issue, it also said that the rates were unreasonably high, according to Shayin.
“We are going to write to the CPCB, informing it about the status. We cannot buy anything which makes the plant uneconomic,” he said. After the contract is awarded, it will take the contractors nine months to install the FGD units, Shayin said.
‘BETTER THAN UP,
PUNJAB UNITS’
According to HPGCL estimates, the PTPS is set to miss the deadline to curb pollution according to the new norms. Asked if the plant could be shut down, Haryana Pollution Control Board member secretary S Narayanan said, “There are reports that say the thermal power plants at Jhajjar and Panipat are comparatively better in handling emissions than those in Punjab and Uttar Pradesh. Technically, Panipat and Jhajjar power stations are more equipped to deal with pollution. But, I have to verify the reports.”
The CPCB did not reply to phone calls and messages for comment.
In the show-cause notice to the power plant, CPCB chairman SP Parihar said, “The PTPS, HPGCL, Haryana, is hereby directed to show cause as to why unit 7 of the plant should not be closed in view of non-compliance.”
On October 9, a CPCB team had found unit 7 to be non-compliant with the prescribed emission standards.
The concentration of PM emissions from the unit was 180.3 milligrams per cubic metre against the prescribed standard of 150 mg/Nm3.
-
Rapid rail to deliver vegetables, milk in Delhi-NCR | What we know
The NCRTC established Regional Rapid Transit System - a rail-based, high-speed regional commuter transit system for Delhi-NCR, will also facilitate transportation of goods, Livehindustan reported. The first RRTS train set arrived at Duhai depot in June from its manufacturing unit in Savli in Gujarat. Delhi-Meerut Rapid Rail Line successfully conducted its first trial on August 7. Here's what we know about the transportation of goods via rapid rail in Delhi-NCR 1.
-
Cloudy sky, light rain expected in Delhi today: IMD
The India Meteorological Department on Wednesday said Delhi is “likely to witness generally cloudy sky with possibility of very light rain or drizzle” on Wednesday. On Tuesday, the average maximum temperature was recorded at 33.1C, which was one degree below the normal temperature around this time of the year. The minimum temperature on Tuesday was 24.6C, which was two degrees below the normal temperature at this time of the year.
-
Scheduled power cuts in Bengaluru from August 17 - 19: Report
Bengaluru's electricity board, the Bangalore Electricity Supply Company Limited, has planned scheduled power outages in the city on August 17 and 18 to undertake maintenance and repair works. Multiple projects were delayed in the city in the midst of relentless rain, such as the shifting of overhead cables underground. Many similar works are underway, which are usually carried out between 10 am to 6 pm.
-
Largest plane Airbus A380 to land in Bengaluru for the first time
Aviation enthusiasts are in for a treat as the world's largest plane, the Airbus A380, will be touching down in Bengaluru's Kempegowda International Airport for the first time on October 30, thanks to Emirates. Bengaluru will be the second Indian city to enjoy the luxury flying experience with the signature double-decker aircraft after Mumbai. The Airbus A380 is known for its extra legroom and large screens across all cabins for in-flight entertainment.
-
Karnataka Home Minister Araga Jnanendra meets top cop over Shivamogga banner row
Taking up the matter of recent clash in the state over portraits of Vinayak Damodar Savarkar and Tipu Sultan, Karnataka Home Minister Araga Jnanendra held a meeting on Tuesday with the Additional Director General of Police Law and Order, Alok Kumar and other senior police officials in Shivamogga. Jnanendra said that nobody should take the law into their hands at any cost.