Karnataka RERA directs developer to pay ₹1.08 crore to homebuyer for delay in possession in Bengaluru’s tallest tower

Bengaluru real estate: Karnataka RERA has directed the developer to pay 1.08 crore to a homebuyer for delay in handing over a flat in the city’s tallest tower

Updated on: Nov 14, 2025, 08:08:14 IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The Karnataka Real Estate Regulatory Authority (KRERA) has directed Bengaluru-based developer Golden Gates Properties Ltd to pay 1.08 crore in delayed interest to a homebuyer for failing to deliver possession of an apartment in Presidential Tower, one of Bengaluru’s tallest residential projects, standing 161 metres high with 50 storeys.

The Karnataka Real Estate Regulatory Authority (KRERA) has directed a Bengaluru-based developer to pay  ₹1.08 crore in delayed interest to a homebuyer for failing to deliver possession of an apartment on time. (Representational photo) (Pexels)
The Karnataka Real Estate Regulatory Authority (KRERA) has directed a Bengaluru-based developer to pay ₹1.08 crore in delayed interest to a homebuyer for failing to deliver possession of an apartment on time. (Representational photo) (Pexels)

According to the order, the buyer had booked a luxury apartment worth nearly 2 crore in 2014, with a promised delivery date of 2017. However, the project, a 50-storey luxury high-rise located in Yeshwanthpur, was delayed for several years, prompting the buyer to file a complaint before the regulator.

“The Respondent is hereby directed to pay delay period interest of 1.08 crore calculated at the rate of SBI MCLR 2% from 2017 till 2024,” the order said. Further, the interest due from 2024 till actual delivery of possession will be calculated likewise and paid to the Complainant,” it said.

The case

In this case, the buyer, Premlatha, entered into a sale agreement with the builder on November 29, 2014, to purchase a flat in A Block of the Presidential Tower project for 1.98 crore and paid 1.5 crore as per the payment schedule.

The developer had promised possession by November 1, 2017, with a four-month grace period, but the flat has not been handed over yet. The complainant, who made all payments on time, has approached the KRERA seeking interest for the delay and directions to complete the project with pending amenities, the order said.

Multiple project extensions

The KRERA order stated that the project’s registration was originally valid from July 1, 2014, to June 30, 2021, and was later extended due to COVID-19 till March 30, 2022. The promoter then applied for an extension under Section 6 of the RERA Act, which was approved until March 3, 2023.

Also Read: KRERA orders BDA to register long-delayed Nadaprabhu Kempegowda Layout project

Since the project was still not completed, the Authority granted another extension under Section 7(3) of the Act, allowing the project to continue until December 31, 2025.

KRERA findings

The KRERA noted that the agreed possession date for the flat was 2017, with an additional grace period of four months as per the sale agreement. “The complainant paid substantial sums and complied with payment obligations, yet the possession has not been handed over to date,” it said.

KRERA said that the developer cited RERA extensions and the pandemic as reasons for the delay. “There is no documentary material placed on record showing that the complainant gave consent to vary the agreed date in the sale agreement or that a fresh agreement varying the contractual date was executed with the complainant,” the order said.

Also Read: Karnataka RERA pulls up Bengaluru real estate developer for not constructing compound wall, misusing undivided share

The authority also clarified that administrative extensions under RERA do not amend private contracts or exempt promoters from paying delay compensation.

KRERA noted that the developer had offered the buyer a one-time concession of 10.5 lakh as a settlement, which the buyer was not bound to accept. The builder cited COVID-19 and force majeure for the delay, but failed to provide specific, month-wise evidence of labour or material shortages affecting the flat’s handover, it said.

Also Read: Bengaluru real estate: Property owners say e-Khata process remains riddled with delays and paperwork

"Despite facing challenges such as financial constraints, labour shortages, and customer-driven unit modifications, our team at Presidential Towers is working tirelessly to ensure the project’s completion within the next 4–6 months. Comprehensive measures have already been implemented to accelerate progress and facilitate the full handover of units to our valued customers. We remain steadfast in our mission to provide world-class residences and uphold the trust placed in us by our customers," the company said in a statement.

  • Souptik Datta
    ABOUT THE AUTHOR
    Souptik Datta

    Souptik Datta is a deputy chief content producer at Hindustan Times Digital, where he reports on southern India with a focus on real estate, urban infrastructure and environmental urban issues. His coverage tracks the intersection of policy, capital flows, regulation and sustainability, examining how these forces shape housing markets, commercial real estate and large-scale infrastructure development across rapidly transforming cities. He also closely tracks civic issues affecting urban residents, including property taxation, planning approvals, public transport expansion, water stress, waste management and the governance challenges that influence everyday life in India’s metros. Souptik’s reporting is driven by a strong interest in accountability, consumer rights and the lived realities of homebuyers and investors navigating volatile pricing cycles, regulatory changes and project delivery risks. He frequently analyses project launches, land monetisation strategies, planning frameworks, RERA-related developments and the broader implications of infrastructure investments on emerging growth corridors. His work blends on-ground reporting with data-backed analysis and long-form explainers aimed at demystifying complex real estate and infrastructure developments for readers. He is an alumnus of the Indian Institute of Journalism and New Media. Before joining Hindustan Times Digital, Souptik was associated with Moneycontrol at Network 18, where he covered real estate, infrastructure and allied sectors, producing market insights, policy-led stories and in-depth features. Outside the newsroom, Souptik is an avid solo traveller and documentary enthusiast, exploring diverse regions and visually documenting unique narratives through film and photography. In his early career, Souptik also freelanced as a documentary photographer, independently working on visual storytelling projects that captured grassroots narratives, urban change and everyday life. He can be reached at souptik.datta@htdigital.in.Read More

Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times