City to get India’s first travelator skywalk linking Metro, Monorail and local trains

MUMBAI: Changing between the Metro, Monorail and suburban railway at Mahalaxmi will soon become significantly easier, with the Mumbai Metropolitan Region Development Authority (MMRDA) completing nearly 90% of a first-of-its-kind multimodal skywalk equipped with travelators

Published on: Jul 27, 2026, 08:36:04 IST
Advertisement

MUMBAI: Changing between the Metro, Monorail and suburban railway at Mahalaxmi will soon become significantly easier, with the Mumbai Metropolitan Region Development Authority (MMRDA) completing nearly 90% of a first-of-its-kind multimodal skywalk equipped with travelators.

City to get India’s first travelator skywalk linking Metro, Monorail and local trains
City to get India’s first travelator skywalk linking Metro, Monorail and local trains

The elevated pedestrian corridor, the first in India to feature moving walkways as part of a public transport interchange, will connect the Sant Gadge Maharaj Chowk Monorail station, Mahalaxmi Metro station on the Aqua Line and Mahalaxmi station on Western Railway’s suburban network. (SEE BOX)

Once operational, the facility is expected to cut transfer time between the three transport systems by almost 20 minutes by allowing commuters to switch modes without stepping onto busy roads or navigating multiple staircases.

The project comes at a time when Mumbai’s Metro network is expanding rapidly, but seamless last-mile connectivity between Metro stations, suburban railways and the Monorail continues to remain one of the city’s biggest challenges. At several interchange points, commuters are still forced to walk long distances or depend on autorickshaws and taxis to complete their journey.

According to MMRDA officials, the facility will be capable of handling around 4,500 passengers every hour and is expected to particularly benefit commuters travelling between south Mumbai, Worli and the city’s central suburbs.

Officials said constructing the project was among the authority’s most complex urban infrastructure assignments because of the maze of underground utilities beneath the site. Before work could begin, engineers had to relocate an 1,800-mm-diameter storm-water drain while ensuring that nearby water supply and sewer pipelines remained fully operational. Construction was also carried out in close coordination with the Mumbai Traffic Police to minimise disruptions on the busy Sane Guruji Marg corridor.

Urban transport planners have long argued that integrated interchange facilities are critical to making public transport more convenient and encouraging commuters to shift away from private vehicles.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe