Historical rail bridge to be dismantled to pave way for concrete girder

Bridge number 20 over Mithi river in Bandra, which has been holding the rail tracks together since 1888, will be replaced by a cement concrete girder

Updated on: Dec 21, 2024, 09:12:51 IST
Advertisement

MUMBAI: One of the last iron screw-pile rail bridge on Indian Railways will soon become history. Bridge number 20 over Mithi river in Bandra, which has been holding the rail tracks together since 1888, will be replaced by a cement concrete girder. The bridge came up around the same time that Bandra railway station was taking shape.

The bridge is a key link between the city and stations like CSMT. (HT Photo)
The bridge is a key link between the city and stations like CSMT. (HT Photo)

There are eight pillars - two on each rail line - underneath the rail tracks on Slow and Fast lines going towards Churchgate and Virar, going east to west. Each pillar is made of cast iron, weighing 8-10 tonne, go down to a depth of 15-20 metres, hitting the bedrock of Mithi River.

The pillars are almost 2 feet or around 600 mm in diametre, with a thickness of 50 mm to ensure that they hold the weight of the steel girders and the rail lines above. The pillars abut the stone wall on the Dadar end, that will also be demolished.

“This is the last remaining screw pile bridge made of cast iron on Indian Railway. We will have to dismantle it as it’s sinking and has become weak. This can prove to be a safety issue for train operations and requires to be replaced. Over the years, we have carried out strengthening works on these piles,” said a Western Railway engineer.

Night rail blocks

Western Railway authorities will carry out two 9.5 hours block in January. According to WR officials, it will take place on the night of January 24-25 and January 25-26, for 9.5 hours each night.

There is no clarity on the number of train services that will be cancelled and delayed during this block, as the schedules are yet to be chalked out. During the two blocks, the engineers will remove the steel girder on top of the piers and replace it with a 20-metre long concrete girder.

“There will be speed restriction of 15-20 kmph for the first 3-4 days after the blocks. We will inspect the strength of the temporary girder placed below, and after clearance, we will allow trains to run at 40 kmph,” said another WR official.

The speed restriction above Mithi River on the Fast and Slow lines between Churchgate and Virar will continue till May. Between January and May, WR will dismantle the iron piers into pieces. Sources said this will lead to delays in train services. Once the work is complete, WR will carry out another round of blocks for cementing the new pillars with concrete and installing girders above these, after which the rail tracks will be placed.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe