Bullet train project: Key milestones achieved at Gujarat’s Vapi station

The National High Speed Rail Corporation Limited (NHSRCL), which is implementing the project, said platform level slab casting and structural steel installation has been completed

Published on: Jun 03, 2025 03:20 PM IST
Advertisement

The structural works at the key Vapi station in Gujarat along the 508-km Mumbai-Ahmedabad High-Speed Rail Corridor, popularly known as the bullet train project, have achieved key milestones, with the completion of rail platform level slab casting and structural steel installation, the implementing agency said.

The station will have a 28,917 square metres built-up area and amenities such as a business class lounge. (Sourced)
The station will have a 28,917 square metres built-up area and amenities such as a business class lounge. (Sourced)

The National High Speed Rail Corporation Limited (NHSRCL), which is implementing the project using Japanese Shinkansen technology, said roof sheeting and electrical installations were in progress. In a statement, it added that the station’s approach viaduct toward Ahmedabad is ready, and work on that towards Mumbai was going on.

The NHSRCL said the Vapi station in Dungra village will have a 28,917 square metres built-up area, rise to around 22 metres, and have amenities such as a business class lounge. The station is about seven km from the Vapi railway junction, 7.5 km from the bus station, and five km from an industrial area. It will be one of 12 stations—Mumbai (Bandra Kurla Complex), Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad, and Sabarmati— along the bullet train corridor.

The full corridor is expected to be completed by 2028 and reduce travel time between Mumbai and Ahmedabad by almost half to under three hours. One train service will halt at all stations (two hours 58 minutes), and another will have limited stops (about two hours seven minutes).

In its latest update, the NHSRCL said 304 km of viaduct and 388 km of pier work have been completed across the project. Fourteen river bridges, seven steel bridges, and five pre-stressed concrete bridges were ready. Around 163 km of track bed construction has also been finished.

The ambitious Japanese-backed project has faced escalating costs, and a major part of the spending has been on infrastructure building. The Japan International Cooperation Agency is funding the construction of the high-speed rail line.

In September 2024, HT reported that the first Shinkansen E5 bullet train meant to ply at speeds up to 320 km per hour will take at least two years to arrive from Japan, as the Indian railways were in talks with its Japanese counterparts to finalise a schedule for supplying the trains.

Prime Minister Narendra Modi announced the project three years before the work began in 2020. The project, spanning Maharashtra (155.76 km), Gujarat (384.04 km), and Dadra and Nagar Haveli (4.3 km), was scheduled to be completed by 2023. Protests against land acquisition delayed the project.

In March 2024, the NHSRCL said all civil contracts have been awarded in Gujarat and Maharashtra. The laying of the first reinforced concrete track bed for the MAHSR corridor track system, as used in Japanese Shinkansen bullet trains, started in Surat and Anand. This was the first time the J-slab ballastless track system was used in India. The NHSRCL said it achieved a remarkable milestone with the completion of the first 350-metre-long and 12.6-meter-wide mountain tunnel in Gujarat’s Valsad district in just 10 months.

The first steel bridge spanning 70 metres and weighing 673 MT has been built across National Highway 53 in Gujarat’s Surat.

In March 2024, the NHSRCL announced the commencement of the work for India’s first seven-kilometre undersea rail tunnel as part of a 21-km-long tunnel between BKC and Shilphata in Maharashtra. Railways minister Ashwini Vaishnaw, who visited Japan last year to sort out issues delaying the project, in February 2024 announced that a 50km stretch between Surat to Bilimoria is expected to open in August 2026.

 
ABOUT THE AUTHOR
Maulik Pathak

He is an Ahmedabad-based journalist with more than two decades of experience. His career spans business journalism and general news, with reporting across politics, crime, governance, public policy, business, industry, infrastructure, energy, ports, aviation, the environment, wildlife and social issues. He began his career in feature writing before moving into business journalism, reporting on companies and sectors including energy, infrastructure, pharmaceuticals, automobiles and real estate. Over the years, his work expanded to politics, courts, crime, public policy, civic affairs, the environment and wildlife. His reporting has taken him from government offices and courtrooms to factory floors, ports, forests and remote villages, covering stories that range from industrial investments and financial markets to elections, conservation and issues affecting everyday life. While many assignments demand the pace of the daily news cycle, others require sustained reporting over months and years to follow developments beyond the headlines. He started his journalism career with the Asian Age in Ahmedabad in 2002 as a feature writer and sub-editor. Since 2022, he has been working with Hindustan Times. Earlier, he worked with Business Standard, DNA, The Economic Times, Mint and The Times of India. His longest stint was with Mint, where he spent more than eight years reporting across multiple beats. During his career, he has worked in both reporting and editing roles, contributing to page planning, local editions and special editorial projects as newsrooms evolved from print-first operations to digital publishing. Early in his career, he also worked on media and documentary projects with an NGO and as a copywriter at a communications agency before returning to journalism. Away from work, he sometimes makes time for a pair of binoculars, table tennis, cinema and the occasional poem.

Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe