Plans to start section of bullet train corridor

The government has set an ambitious deadline for completing the project by August 15, 2022. Protests over inadequate compensation have slowed down the land acquisition process for the project.

Updated on: Jul 7, 2019, 08:24:51 IST
Advertisement

A temporary depot, use a new technology to lay girders and other time-saving measures are being planned to operationalise at least one section of the India’s first superfast bullet train corridor by August 15, 2022 when the project is scheduled to be completed, according to the project’s executing agency.

The national high speed rail corporation (NHSRCL), which is executing the project, will award the tender for the 237-km elevated section by the year end. It will leave 30 months for the completion of the civil work involved. (HT Photo)
The national high speed rail corporation (NHSRCL), which is executing the project, will award the tender for the 237-km elevated section by the year end. It will leave 30 months for the completion of the civil work involved. (HT Photo)

Prime Minister Narendra Modi and his Japanese counterpart, Shinzo Abe, laid the foundation stone for the Mumbai-Ahmedabad bullet train project in 2017 to mark India’s shift to highspeed trains and as part of efforts to upgrade the country’s infrastructure..

The government has set an ambitious deadline for completing the project by August 15, 2022. Protests over inadequate compensation have slowed down the land acquisition process for the project. About 35% of the land required for the project has been acquired so far, according to the managing director of NHSRCL.

The national high speed rail corporation (NHSRCL), which is executing the project, will award the tender for the 237-km elevated section by the year end. It will leave 30 months for the completion of the civil work involved.

The temporary depot will be built in Gujarat’s Surat to keep trains in case the government decides to open the elevated section of the project first.

“We will open the tender [for the elevated section] in August and will award it by the year end. The expected cost of the civil work of this 237-km section is ₹20,000 crore. This includes the temporary depot in Surat in case we will have to open this section before August 15, 2022...,” said NHSRCL managing director, Achal Khare. The corporation will ask the contractor to use full span launching method for laying girders, which will also save time.

 
ABOUT THE AUTHOR
HT News Desk

Follow the latest breaking news, major developments and agenda-setting stories from India and around the world with the newsdesk at Hindustan Times. Operating round the clock, the desk brings together experienced editors, reporters and correspondents to deliver fast, accurate and contextual reporting across subjects that influence public policy, governance, business, society and international affairs. The HT News Desk covers politics, elections, government policies, the economy, business and markets, science and technology, the environment, law and order, infrastructure, education, climate issues and geopolitics, while closely tracking developments across states, institutions and global capitals. The team also leads coverage of major breaking news events, policy announcements, court proceedings, natural disasters, public emergencies and significant international developments. Reports published by the newsdesk are based on information gathered from reporters on the ground, official statements, government agencies, court records, regulatory filings, recognised institutions and other authoritative sources. Stories undergo editorial scrutiny and verification processes to ensure accuracy, fairness and relevance, and are updated as events evolve and additional information becomes available. Whether covering a key political decision in New Delhi, an economic policy shift affecting millions, a landmark court ruling or a major global event, the HT News Desk aims to provide readers with reliable, fact-based journalism that delivers not only the latest developments but also the context and analysis needed to understand their wider implications.

Get Latest News, breaking headlines, and top India News, and today real-time updates from across the nation. Stay informed on politics, government policies, crime, Today Weather, and major developments on Hindustan Times
Get Latest News, breaking headlines, and top India News, and today real-time updates from across the nation. Stay informed on politics, government policies, crime, Today Weather, and major developments on Hindustan Times
SHARE THIS ARTICLE ON
Notifications

Get breaking alerts directly from the newsroom

Notifications are on!You'll be notified when news breaks