Metro at Mumbai’s Aarey: MRCL didn’t get pollution board nod

MPCB officials from told HT that the MMRCL has not applied for consent to establish or operate the Metro car-shed, stabling lines or a casting yard in Aarey Milk Colony in the last two years...

Updated on: Jan 10, 2017, 01:02:29 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

The Mumbai Metro Rail Corporation Limited’s plan to build a car shed and stabling lines in the city’s green lung Aarey Colony faces another hurdle.

An MPCB official said that since MMRCL is a ‘red category industry’ (identified by Ministry of Environment Forests and Climate Change as heavily polluting), it needs to get clearances from local authorities. (HT file)
An MPCB official said that since MMRCL is a ‘red category industry’ (identified by Ministry of Environment Forests and Climate Change as heavily polluting), it needs to get clearances from local authorities. (HT file)

While the National Green Tribunal (NGT) has already terminated all construction, including for the Metro III project, at the site, the state pollution control board has now said MMRCL did not take their permission to build a car-shed or stabling lines.

Maharashtra Pollution Control Board (MPCB) officials told HT MMRCL had not applied for permission in the past two years. “MMRCL got environment clearances (EC) from the Union environment ministry as per the eco-senstive zone notification, but conditions of the EC need to be monitored and verified by the local pollution board,” said a senior MPCB official, requesting anonymity. “For this, the metro rail corporation needs to apply for consent from MPCB. On an average, it takes 120 days to clear such an application.”

The official said MMRCL was a ‘red category industry’ — identified by the Ministry of Environment Forests and Climate Change as heavily polluting — and needed clearances from local authorities under the Air (Prevention & Control of Pollution) Act, 1981 and Water (Prevention and Control of Pollution) Act, 1974. On December 5, the Union environment ministry passed a final notification on the buffer zone — an area meant to protect the environment — around Sanjay Gandhi National Park (SGNP) up to 4km from its boundary. It proposed development and construction work at Aarey, which falls under the permitted eco-sensitive zone. The notification identified the exclusion of 165 hectares from Aarey where construction will be allowed, including for the Metro project. But the notification was published with a rider — that it can only be cleared subject to Supreme Court, high court and NGT orders.

Also read:NGT ban on construction: Aarey cement plant gets show-cause notice

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe