Metro-3 cuts its pathtowards smoother travelTunneling of two Metro-3 stations to be completed by Dec 12

The Mumbai Metro Rail Corporation (MMRC) is set to complete 100% tunnelling work between Marol Naka and Seepz — as part of the 33.5-km Metro-3 corridor — by December

Published on: Dec 9, 2019, 00:48:29 IST
Advertisement

The Mumbai Metro Rail Corporation (MMRC) is set to complete 100% tunnelling work between Marol Naka and Seepz — as part of the 33.5-km Metro-3 corridor — by December 12. Around 2,500 workers and more than 350 equipment are at work on the 7.09-km Marol Naka-Seepz stretch, which will be the first of the seven packages of the underground Metro corridor to be completed.

HT Image
HT Image

MMRC, which is executing the Colaba-Bandra-Seepz line, has completed 70% of the tunnelling on the entire stretch with 23 tunnel breakthroughs. The 24th tunnel breakthrough is expected next week at Seepz.

The corridor, which has been touted as one of the most challenging projects ever, is being executed by 16,000 people

When HT visited two underground stations on the Marol Naka-Seepz stretch (package number 7) — the Marol Naka station and the Maharashtra Industrial Development Corporation (MIDC) station — it found that 800 cubic meters of concrete was being used to create slabs.

At Marol Naka, the Metro-3 corridor will be running beneath the elevated Metro-1 (Versova-Andheri-Ghatkopar) corridor. With pillars of Metro-1 coming in the way of Metro-3’s alignment, MMRC is constructing two station boxes on either side of the former. “These two boxes will be connected via 12 cross passages for passengers at the platform level,” said a site engineer at Marol Naka.

The MIDC station, which is 21m below ground level, will provide much-needed connectivity to the isolated industrial area. The station’s structure appeared to be more complete than Marol Naka station. A site engineer at MIDC said, “We have completed 78% of the concourse slab and 58% of the roof slab. In fact, we have also started construction of boxes for the control room and signalling system at the concourse level.” The MIDC station is 240m in length with four entry-exits points.

While the state has put a stay on the construction of the Metro-3 car shed in Aarey, all seven packages of the corridor have completed more than 50% tunnelling. Once operational, Metro-3 is expected to cater to 17 lakh passengers, reducing an estimated 6.5 lakh car trips every day.

 
ABOUT THE AUTHOR
Tanushree Venkatraman

Tanushree Venkatraman is a Multimedia Correspondent covering civic issues and governance in Mumbai.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe