Mumbai Urban Transport Project-3 for Central Railway, Western Railway: On slow track since ‘16

No clarity on funds; project, aimed at improving connectivity in Mumbai Metropolitan Region, is stuck; World Bank to give decision by December

Updated on: Sep 9, 2018, 23:58:15 IST
Hindustan Times | By
Prefer HTon Google
Advertisement

Almost two years after getting Cabinet nod, the Mumbai Urban Transport Project (MUTP) 3, a project aimed at boosting rail connectivity in the Mumbai Metropolitan Region (MMR), is stuck for want of funds.

Of the estimated cost of ₹10,948-crore, ₹6,000 crore has been sought from the World Bank. (PHOTO FOR REPRESENTATION)
Of the estimated cost of ₹10,948-crore, ₹6,000 crore has been sought from the World Bank. (PHOTO FOR REPRESENTATION)

Of the estimated cost of 10,948-crore, 6,000 crore has been sought from the World Bank. According to the Mumbai Rail Vikas Corporation (MRVC), the nodal agency responsible for executing major infrastructure projects related to suburban railways, the World Bank is studying and reviewing the projects. “Talks with World Bank over the funding are going on. We are expecting a final decision by December,” said RS Khurana, chairman and managing director, MRVC.

Railway officials feel MUTP-3 may miss its 2022 deadline, despite major infrastructure projects being expedited. “After we get an official nod from the World Bank, we will take a minimum of nine months to finish tendering, issue work orders and complete other formalities. Although a few parts of the project might begin, the main work is likely to start only by the end of 2019. Meeting the deadline seems difficult,” said a senior MRVC official.

The MRVC has expedited the work on the Panvel-Vasai-Virar corridor and included it in under MUTP-3. All these corridors will provide connectivity to areas witnessing substantial real estate development around the new international airport and is expected to decongest the city. However, without rail connectivity, it will be difficult to populate the many smart cities that are coming up in these areas.

While MUTP-3 is delayed, the 55,000-crore next phase, MUTP-3A, has been sent to the railway board for nod in June. The project will go to Niti Aayog, after the Union cabinet gives final nod. The deadline is 2023.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe