No Mumbai-Pune trains for 15 days from July 26

The cancellation of 20 trains is expected to cause significant inconvenience to those travelling between the two cities.

Updated on: Jul 25, 2019, 01:15:51 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

The Mumbai division of Central Railway (CR) has announced that 18 intercity trains to Pune or passing via Pune from Mumbai, will be fully or partially cancelled between July 26 and August 9. Mumbai-Pune is one of the busiest train routes.

CR said the decision was taken to carry out infrastructure works at Bhor Ghat, located above 110-km from Mumbai between the Karjat and Lonavala section. (HT File)
CR said the decision was taken to carry out infrastructure works at Bhor Ghat, located above 110-km from Mumbai between the Karjat and Lonavala section. (HT File)

The cancellation of 20 trains is expected to cause significant inconvenience to those travelling between the two cities.

CR said the decision was taken to carry out infrastructure works at Bhor Ghat, located above 110-km from Mumbai between the Karjat and Lonavala section. Train services have been affected in this section due to cases of boulders falling since mid-June. “We have planned major infrastructure upgrade during this period to ensure smooth services are maintained in coming times,” said Sunil Udasi, chief public relations officer of CR.

Of the six direct trains between Mumbai and Pune, Deccan Express and Pragati Express will remain cancelled, along with the Pune-Panvel-Pune Express. Deccan Queen, Sinhagad Express and Indrayani Express will run as per schedule. In addition, the Mumbai-Gadag Express will also remain cancelled.

Bhusawal-Pune-Bhusawal Express, which usually goes via Panvel, will be diverted and take the Manmad-Daund route. “CR is holding passengers ransom by cancelling 20 trains between Mumbai and Pune,” said Harsha Shah, chairman of Railway Pravasi Sangh.

There are concerns that the cancellations will lead to overcrowding in the existing trains and force many to travel by road.

Before the monsoon, CR completed works worth more than 6 crores, including removing boulders from 700 vulnerable locations, installing 60 additional CCTV cameras, setting up Canadian fencing at 650 metres (to prevent boulders falling on tracks) and extending tunnel portions at four locations.

 
ABOUT THE AUTHOR
Kailash Korde

Kailash works with the political team and has been covering transport beat for over a decade. He is interested in travel and music.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe