PM Modi to review progress of Delhi-Meerut expressway on Aug 28

Two issues that loom over phase 2 and phase 4 of the Delhi-Meerut Expressway project are the possession of a patch of land and a payment of ₹85 crore that the authority is yet to receive from the UP government.

Published on: Aug 26, 2019 03:22 PM IST
Hindustan Times, Ghaziabad | By , Ghaziabad
Prefer HTon Google
Advertisement

Prime Minister Narendra Modi will review the under-construction Delhi-Meerut Expressway (DME) project on August 28 to resolve all pending issues.

The Delhi-Meerut Expressway project is being built in four phases. The first phase from Akshardham in Delhi to UP Gate is already operational. (Sakib Ali / HT Photo)
The Delhi-Meerut Expressway project is being built in four phases. The first phase from Akshardham in Delhi to UP Gate is already operational. (Sakib Ali / HT Photo)

Officials of the National Highways Authority of India (NHAI) said they will put forward unresolved issues during the‘Pragati’ review meeting to be chaired by the PM. Two issues that loom over phase 2 and phase 4 of the project are the possession of a patch of land and a payment of 85 crore that the authority is yet to receive from the Uttar Pradesh government.

The DME project includes four phases. The first phase of the project from Akshardham in Delhi to UP Gate is already operational, while the NHAI is working on three remaining phases which are under the UP state government’s jurisdiction.

Officials said during the Pragati meetings, the PM reviews major infrastructure projects and gives instructions for resolution of any pending issues.

“During the review meeting on August 28, we will be put forward two pending issues. One is about a 7km long stretch of land whose physical possession we have not been able to get for phase 4 of the project (Dasna to Meerut). This is hampering the progress of work and causing delays in completing the project. An inquiry is pending at the state government level and their clearance is needed,” project manager (NHAI), RP Singh, said.

The officials will be interacting with the PM through ‘Pragati’ platform—an ICT-based, multi-modal platform. The platform is aimed at proactive governance and timely implementation of major infrastructure projects.

According to NHAI officials, phase 3 from Dasna to Hapur is nearing completion and is likely to be made operational by the first week of September. Phase 2, UP Gate to Dasna is likely to be open in December 2019 against the scheduled opening in May 2020.

Likewise, phase 4 which comprises the Greenfield Expressway from Dasna to Meerut is likely to open in December 2019 against its scheduled time of completion in August. The officials said physical possession of the 7km stretch is delaying the project.

 
ABOUT THE AUTHOR
Peeyush Khandelwal

Peeyush Khandelwal writes on a range of issues in western Uttar Pradesh – from crime, to development authorities and from infrastructure to transport. Based in Ghaziabad, he has been a journalist for almost a decade.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe