27 Hoshiarpur highway projects delayed: Gadkari to Parliament

Land acquisition, pending approvals affecting 14 national highway, 13 state road projects, Union highway minister says while replying to a query of Hoshiarpur MP Raj Kumar Chabbewal

Published on: Feb 13, 2026, 03:48:12 IST
Advertisement

A majority of highway projects approved in Punjab’s Hoshiarpur under the Central Road Infrastructure Fund (CRIF) Scheme in 2024 have faced significant delays due to land acquisition issues, pending administrative approvals and other clearances, the Union ministry of road transport and highways informed Parliament on Thursday.

Union minister of road transport and highways Nitin Gadkari (PTI file)
Union minister of road transport and highways Nitin Gadkari (PTI file)

Responding to an unstarred question in the Lok Sabha, road transport and highways minister Nitin Jairam Gadkari said 29 highway projects, including 16 national highway projects and 13 state-road projects, were inaugurated or had their foundation stones laid in 2024 in Hoshiarpur under the central scheme. Of the national highway projects, 14 have been affected due to delays in handing over of land, statutory clearances and approval of general arrangement drawing (GAD) of railway road overbridges and under bridges, and force majeure events, such as heavy rainfall.

Out of 13 state road projects, six have not received administrative approval from the state government, whereas the progress/award of remaining seven projects is affected due to delay in handing over of land, statutory approvals, etc, the minister said in a written reply to Hoshiarpur MP Raj Kumar Chabbewal’s question. In his query, Chabbewal had sought reasons for the delays, details of cost escalation and measures being taken to ensure the completion of these road projects in a time-bound manner.

The ministry said that various initiatives have been taken to avoid or reduce project delays, including streamlining land acquisition and environment clearances, and revamping dispute resolution mechanism.

“Development and maintenance of NHs is a continuous process. Works on NHs are accordingly taken up based on the traffic density, condition of road and synergy with PM Gati Shakti National Master Plan to keep the NHs in traffic worthy condition,” it added.

 