NCRTC seeks direct land purchase policy for Haryana RRTS corridors

Corporation flags delays under RFCTLARR Act, seeks faster acquisition for two Namo Bharat corridors; proposal under state government review.

Updated on: Mar 23, 2026 07:51 AM IST
Advertisement

The National Capital Region Transport Corporation (NCRTC) has asked the Haryana government to approve a direct purchase policy for land acquisition for two Namo Bharat Regional Rapid Transit System (RRTS) corridors, citing the need to expedite project execution.

Move aims to speed up acquisition for SKK-Panipat-Karnal and Gurugram-Bawal corridors. DPRs approved; proposal under consideration. (HT Archive)
Move aims to speed up acquisition for SKK-Panipat-Karnal and Gurugram-Bawal corridors. DPRs approved; proposal under consideration. (HT Archive)

In a February 19 communication to the state government, NCRTC managing director Shalabh Goel said the existing land acquisition process under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013, is time-consuming and could delay the projects. “In view of the importance, scale, and time-bound nature of the Namo Bharat RRTS projects, it is respectfully requested that a similar direct purchase policy may kindly be considered and approved for land acquisition for the Namo Bharat RRTS corridors as well,” Goel said.

The request follows Haryana’s recent approval of a direct purchase policy for Gurugram Metro Rail Limited (GMRL), which allows land procurement through mutual negotiations with landowners via a district land purchase committee headed by the deputy commissioner. GMRL has already initiated the process and held meetings with landowners.

The corporation requires 202.98 hectares of government land and 154 hectares of private land for the two corridors. A tender for construction of the Delhi-Gurugram-Bawal corridor is expected to be floated within a month.

A senior HMRTC official said the proposal is under consideration. “The direct land purchase policy for the Gurugram metro has been recently approved to ensure faster acquisition of land and compensation to owners. It will also help in starting the construction work early,” the official said, adding that the town and country planning department is likely to submit a report soon.

As per the revised DPR for the Delhi-Gurugram-Bawal corridor, land acquisition is planned between December 2025 and November 2027. Preliminary investigation and detailed design will run concurrently, followed by construction of elevated structures between August 2026 and August 2030 and underground works till January 2031. Track laying, signalling and related works are scheduled for completion by June 2031, with testing between May and October 2031 and commissioning by November 2031.

 
ABOUT THE AUTHOR
Abhishek Behl

Abhishek Behl is principal correspondent, Hindustan Times in Gurgaon Bureau. He covers infrastructure, planning and civic agencies in the city. He has been covering Gurgaon as correspondent for the last 10 years, and has written extensively on the city.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe