After locals oppose, MSRDC to change alignment of Pune ring road

After opposition to the passage of the Pune ring road via tunnel through Maval tehsil’s Bhandara dongar which is considered sacred by the locals, MSRDC has initiated an assessment procedure for change in alignment of the road

Updated on: Sep 15, 2021 04:28 PM IST
By
Prefer HTon Google
Advertisement

Following opposition to the passage of the Pune ring road via tunnel through Maval tehsil’s Bhandara dongar which is considered sacred by the locals, the Maharashtra State Road Development Corporation (MSRDC) has initiated an assessment procedure for change in alignment of the eastern part of the road near the said hill. Officials said that the original plan for the road to pass through the hill has been dropped and assessment is slated to begin to shift the route from the base of the hill.

The assessment of various factors related to the change in alignment of the Pune ring road such as its impact on the project budget, distance, land requirement and proximity of other national highways is scheduled to begin from September 14 and will take at least a month to complete as per MSRDC officials (HT PHOTO)
The assessment of various factors related to the change in alignment of the Pune ring road such as its impact on the project budget, distance, land requirement and proximity of other national highways is scheduled to begin from September 14 and will take at least a month to complete as per MSRDC officials (HT PHOTO)

The assessment of various factors related to the change in alignment such as its impact on the project budget, distance, land requirement and proximity of other national highways is scheduled to begin from Tuesday and will take at least a month to complete as per MSRDC officials.

Sandeep Patil, sub-divisional engineer, MSRDC, said, “There are emotions attached to the Bhandara dongar. Now we have to do an assessment for this change in alignment. We will need to assess how much extra land would be required if the ring road is to be shifted from the base of the hill and how many houses would be affected. The new alignment will have to be planned keeping in mind that the Chakan-Shikarpur national highway is nearby. Consultants will conduct this study and its economical impact will also have to be assessed. It will take a month.”

On September 6, the state government approved 26,831.21 crore for the Pune ring road project, including construction and land acquisition costs. Out of 26,831.21 crore, 12,175.97 crore has been allocated for the western part of the ring road. Land survey of only three out of the 37 affected villages remains to be done for the western part. Collectively, 14,655.24 crore has been allocated for the eastern part. The Pune ring road is a proposed circular, outer road for the Pune Metropolitan Region, expected to solve the traffic woes of the Pune and Pimpri-Chinchwad cities. For the 173 km ring road, a total of 1,526.1153 hectare area is required.

 