Total land needed for Jewar airport Phase 1 to be acquired by Jan 23

The Gautam Budh Nagar administration, on Wednesday, said it will complete the job of taking physical possession of 1,239.14 hectares, needed to build phase-1 of

Published on: Jan 15, 2020, 23:57:26 IST
Advertisement

The Gautam Budh Nagar administration, on Wednesday, said it will complete the job of taking physical possession of 1,239.14 hectares, needed to build phase-1 of the Noida International Greenfield Airport, by January 23. A team of Zurich Airport International AG met officials of NIAL and UP civil aviation department to discuss the project.

HT Image
HT Image

“We only need to take physical possession of remaining 72.42 hectares from farmers of six villages—Ranhera, Parohi, Rohi, Kishorpur, Dayanatpur and Banwaribas—as they have refused to give land for the project. As per Section 76/77 of Land Act, 2013, we have deposited 179.54 crore in the tribunal from where farmers can collect the compensation. As per rules, we have started taking possession of this land and we will finish the job by January 23, 2020,” sub-divisional magistrate Abhay Kumar Singh, nodal officer of land acquisition for Jewar airport, said.

Once the administration takes physical possession of the land, it will be handed over to the Yamuna Expressway industrial development authority (Yeida) and the Noida International Airport Limited (NIAL). Later, these two agencies will hand over the land to the airport concessionaire, Zurich International AG, which will start construction.

Work on the airport project, which will come up along the 165km Yamuna Expressway connecting Greater Noida with Agra, is expected to start in the next two months, as soon as Zurich International AG forms a special purpose vehicle (SPV), which will seek clearances from the Union ministry of home affairs.

On the whole, the Noida International Airport Limited needs to acquire 5,000 hectares for the four-phase project. In phase-1 it needs to acquire 1,239.14 hectares, most of which have been acquired and the physical possession taken.

Meanwhile, the NIAL is mulling over a proposal to hire an agency that can conduct a survey for phase-2 of the airport project. The NIAL and the Yeida want to conduct a survey to ascertain when work can be started on phase-2. “The request for proposal to select agency for the survey is likely to be drafted soon,” said a NIAL official not authorized to speak to the media.

 
ABOUT THE AUTHOR
Vinod Rajput

Vinod Rajput writes on environment, infrastructure, real estate and government policies in Noida and Greater Noida. He has reported on environment and infrastructure in Delhi, Gurgaon and Panchkula in the past.

Stay updated with all the breaking news and latest News from Mumbai. Track comprehensive coverage of top cities across India including Bengaluru, Delhi (including Sonam Wangchuk Hunger Strike LIVE),and more, along with staying informed on the latest happenings.
Stay updated with all the breaking news and latest News from Mumbai. Track comprehensive coverage of top cities across India including Bengaluru, Delhi (including Sonam Wangchuk Hunger Strike LIVE),and more, along with staying informed on the latest happenings.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe