12 years on, Mumbai civic body’s plan to reduce flooding not even half done

Mumbai city news: Tenders for some projects to improve drainage capacity of pipelines post the 2005 deluge not yet issued

Updated on: Jun 18, 2017, 01:38:07 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

While the Brihanmumbai Municipal Corporation (BMC) grapples with complaints of flooding every year, ambitious projects that were planned after the July 26, 2005 deluge are not even halfway done.

After the July 26, 2005 deluge, the BMC had planned the Brihanmumbai storm water disposal system (Brimstowad) project. (Hindustan Times)
After the July 26, 2005 deluge, the BMC had planned the Brihanmumbai storm water disposal system (Brimstowad) project. (Hindustan Times)

After the deluge, the BMC had planned the Brihanmumbai storm water disposal system (Brimstowad) project.

The plan involved eight pumping stations and 58 projects to improve the city’s century-old pipelines.

But in the past 12 years, the BMC has finished fewer than half of the projects.

According to civic data, of the 58 projects, planned in two phases, only 28 have been completed, while 27 are still in progress.

The data revealed that the BMC has not even issued tenders for three projects.

There are 11 projects currently in progress in the eastern suburbs, nine in the western suburbs and three in the island city.

The water-receding capacity of the city’s drains is about 25-30mm an hour, which will increase to 50mm an hour once Brimstowad is completed.

Of the eight pumping stations, the BMC is yet to inaugurate the Guzderbandh pumping station, which has missed two deadlines — May 31 and June 9.

Senior civic officials said they are hoping to complete the process as soon as possible.

“The work is dependent on a lot on approvals from other agencies. Till we don’t get that sorted, we cannot issue tenders,” the official said.

Currently, Haji Ali, Lovegrove and Cleveland at Worli, Irla at Juhu and Britannia at Reay Road are functional. On Monday night, however, when the city received heavy rains, there was a delay in starting operations at Britannia, which would have prevented major flooding at Hindmata, officials said.

That day, the city reported flooding at 41 locations.

The chief engineer of the storm water drains (SWD) department also received a show-cause notice from the additional municipal commissioner for this and for not completing the Guzderbandh pumping station.

Officials from the SWD department said that the station at Guzderbandh has been delayed because the BMC only recently got the Centre’s approval to cut mangroves in Khar-Danda.

 
ABOUT THE AUTHOR
Tanushree Venkatraman

Tanushree Venkatraman is a Multimedia Correspondent covering civic issues and governance in Mumbai.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe