A long and torturous flight ahead for the Navi Mumbai airport

After its inception in 1997, it took a decade for Mumbai’s second airport near Panvel to reach the drawing board. It took another decade to find a builder

Updated on: Feb 14, 2017, 09:02:38 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

After its inception in 1997, it took a decade for Mumbai’s second airport near Panvel to reach the drawing board. It took another decade to find a builder.

Although the City and Industrial Development Corporation (CIDCO) has set a deadline to get the airport ready by May 2020, industry experts feel that the project is unlikely to have it smooth. (HT)
Although the City and Industrial Development Corporation (CIDCO) has set a deadline to get the airport ready by May 2020, industry experts feel that the project is unlikely to have it smooth. (HT)

Although the City and Industrial Development Corporation (CIDCO) has set a deadline to get the airport ready by May 2020, industry experts feel that the project is unlikely to have it smooth.

“The project is likely to see challenges in terms of funds. And keeping in mind the volatile nature of the aviation sector, a major surge in international crude prices would have an impact on the timeline,” said a senior executive with an aviation think tank.

On Monday, the Mumbai International Airport Limited (MIAL), the GVK-led private consortium that operates the Chhatrapati Shivaji International Airport (CSIA), won the bid to build the new airport

Experts said that even if it the project meets the new deadline, air travel out of Mumbai will continue to be chaotic for at least another four years. From handling less than 25 million passengers in 2006, the CSIA entered the big league of the world’s busiest airports by catering to 41.7 million passengers in 2015-16. Industry projections indicate that the clock has begun ticking for the city airport to hit saturation in the next two years.

A comparison of Mumbai’s air traffic planning structure with Istanbul and Dubai showed a dismal picture. In 2014, the Istanbul Ataturk airport handled 56 million fliers, but the airport has already invested US$8 billion for a bigger airport with six runways, four terminals and a capacity to handle 150 million passengers a year. Similarly, Dubai airport, which saw 70 million air passengers in 2014, is being prepared to accommodate 100 million passengers by 2020. The city, with a population of more than 2 million, has started building its second airport at the Dubai Central World, with an estimated capacity for 260 million passengers, the report said.

Mumbai is projected to hit saturation by 2018. Even if the second airport is ready in the next five years, Mumbai would need a third airport by 2035.

READ MORE

Mumbai’s airport operator set to build Navi Mumbai airport

 
ABOUT THE AUTHOR
Soubhik Mitra

Soubhik Mitra is an assistant editor with the Hindustan Times. The Mumbai boy has spent over a decade reporting on civic, environmental and political issues. His current stint is the longest where he writes on aviation and travel.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe