Sign in

MMRDA report blames Reliance Infra-Astaldi for Metro 4 mishap at Mulund

The probe report blamed RAJV on several grounds, including taking shortcuts, and ignorance of duty by the welder, the site supervisor, and the engineer.

Published on: Mar 25, 2026 5:32 AM IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Mumbai: Reliance Infrastructure-Astaldi Joint Venture (RAJV), the infrastructure firm constructing substantial portions of the Metro 4 corridor, was squarely responsible for the accident in Mulund on February 14, when a precast parapet segment fell on an autorickshaw and a car beneath, killing one person and injuring three others, a probe by the Mumbai Metropolitan Region Development Authority (MMRDA) has found.

At Mulund, the 6 feet x 4 feet parapet segment was erected on the carriageway and secured in place with temporary fasteners on the night of February 13. The next day, however, the fasteners were “inadvertently” cut off by the welder even though the segment had not been stitched, the probe found (Hindustan Times)
At Mulund, the 6 feet x 4 feet parapet segment was erected on the carriageway and secured in place with temporary fasteners on the night of February 13. The next day, however, the fasteners were “inadvertently” cut off by the welder even though the segment had not been stitched, the probe found (Hindustan Times)
Litany of lapses
Litany of lapses

The probe report, submitted by Director (Projects) at MMRDA Basavraj M Bhadragond to MMRDA Commissioner Sanjay Mukherjee last week, blamed RAJV on several grounds, including taking shortcuts, resorting to unsafe behaviour, and ignorance of duty by the welder, the site supervisor, and the engineer. It held the contractor, the welder, the site supervisor, the site engineer and the project manager responsible for the incident.

According to the report, which HT has accessed, when such precast segments are used for construction of elevated road/ rail carriageways, they must be secured with temporary metal fasteners; and the fasteners must be removed only after the segments have been ‘stitched’ to the carriageway using construction adhesive.

At Mulund, the 6 feet x 4 feet parapet segment weighing 1.8 tonne was erected on the carriageway and secured in place with temporary fasteners on the night of February 13. The next day, however, the fasteners were “inadvertently” cut off by the welder even though the segment had not been stitched to the carriageway, the probe found.

“On February 14, the engineer instructed the site supervisor to assign to the welder the task of cutting the hook of casted stitched parapets only…The welder cut the parapet’s hook without ensuring proper stitching and support and without informing the concerned supervisor. This caused the 1.8-tonne parapet to become unstable and fall onto the road,” the report said.

The MMRDA did not find any lacunae in the precast parapet segment’s technical parameters such as structural design, material and workmanship. But it identified several procedural and supervisory lapses – such as the contractor did not conduct a joint inspection or checklist confirming the readiness for removal of temporary support for parapet segments; no written authorisation was available prior to support removal; support removal activity proceeded without an approved method statement, though one was available; and no marking system existed to distinguish structurally completed segments from incomplete ones.

RAJV secured the contract for constructing significant portions of the Metro 4 corridor including the Mulund stretch in June 2018. Though the MMRDA bypassed the firm in May 2022 and gave the remaining work to subcontractor Milan Road Buildtech on account of delays, RAJV remained the contractor on record.

Shortly after the slab collapsed on February 14, the MMRDA levied a penalty of 5 crore on RAJV for the incident, including because no representative of the firm was present on site at the time. The General Consultant (a consortium of DB, Hill International, and Louis Berger) was also fined 1 crore, while its services were terminated on February 18.

The family of the deceased, Ramdhani Yadav, received 39.5 lakh as compensation, while the three injured persons received hospitalisation costs, totalling 27.59 lakh.

Reliance Infrastructure did not respond to Hindustan Times’ email seeking comments on the probe findings.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.