Gokhale bridge work hits log jam as BMC needs more space to enable crane movement

Officials said the bridges department had initially requested 10meters clearance from the ward which was complete. However, the contractor now needs more space to maneuver the crane and the structures that were partially demolished will have to go completely

Updated on: Aug 29, 2023, 00:39:45 IST
Advertisement

Mumbai: The reconstruction of Gokhale Bridge, a key Andheri east-west connector, has once again hit a log jam. The Brihanmumbai Municipal Corporation’s (BMC) bridges department wants 13 structures on the Andheri east side to be demolished for better movement of a crane that was brought in recently to assemble the girder.

Mumbai, India - Aug 28, 2023 : The BMC wants to remove 13 structures from Gokhale bridge site in Andheri east. Construction of Gokhale Bridge in Andheri east withÊCranesÊatÊwork, in Mumbai, India, Monday, Aug 28, 2023. (Photo by Vijay Bate/HT Photo)
Mumbai, India - Aug 28, 2023 : The BMC wants to remove 13 structures from Gokhale bridge site in Andheri east. Construction of Gokhale Bridge in Andheri east withÊCranesÊatÊwork, in Mumbai, India, Monday, Aug 28, 2023. (Photo by Vijay Bate/HT Photo)

An official from the BMC said the bridges department has requested the K east ward to clear these structures to make room so as to enable the maneuverability of the crane.

While the 13 structures are coming in the way of the construction of the bridge, civic officials have raised concern about the demolitions and evictions since the same cannot be undertaken during the monsoon season as per court orders.

Officials said the bridges department had initially requested 10meters clearance from the ward which was complete. However, the contractor now needs more space to maneuver the crane and the structures that were partially demolished will have to go completely.

“Of the 13 structures, four are legal and will have to be completely displaced under PAPs (project affected people). The procedure for these four will start soon. The remaining nine structures are encroached. But the latter can only be demolished in October since the demolition and eviction cannot be undertaken during monsoon as per court orders,” said a civic official.

On Friday, P Velrasu, additional commissioner (Projects), along with other senior officials of the BMC’s bridges department and ward visited the site to check the progress.

On Friday, Velrasu said, “Progress is satisfactory. All agencies are working in a synchronised manner. There are immediate issues concerning removal of some encroachments, of a billboard in railway premises etc. All the agencies are working together and if there is not much rain, we might open one side of the bridge as per schedule during Diwali.”

The CAG report on Gokhale bridge had said that the demolition and reconstruction of the bridge was delayed by almost four years. “Audit observed that even after the serious incident of collapse of a part of the GKG Bridge in July 2018 and recommendations of the structural auditor, the BMC did not plan for the reconstruction of the bridge in a timely manner.

“Instead, Western Railways with the concurrence of the BMC carried out heavy repair works to steel girder pathway and PSC girder span on the bridge along with repair of the pipeline bridge from October 2018 to February 2020 on deposit basis with funds from BMC at a cost of 6.14 crore.

The BMC should have planned for the reconstruction of the bridge immediately following the recommendations of the structural auditor.”

It added, “The approach road demolition and reconstruction were started in April 2020 while the demolition work of the railway portion of the bridge started in November 2022 and reconstruction work started in January 2023.

“The bridge was completely closed for public use from 07 November 2022. Thus, the demolition and reconstruction work of the bridge was delayed by almost four years.”

The bridge, a part of which collapsed in 2018, killing two, is a key connector between Andheri east and west, and is one of the busiest routes in that suburb. Following the collapse, the bridge was kept partially open while the BMC worked on rebuilding it in phases.

The collapse also triggered the BMC to announce routine audits of all the bridges in Mumbai. It was during this audit in September 2022 that announced the bridge as unsafe forcing it to be completely shut from November 7, 2022.

Carnac bridge delayed again

The BMCs reconstruction of the 150-year-old Carnac Bunder bridge has hit a roadblock due to non-availability of land as there are 12 unauthorised structures on the road — abutting two administrative wards. The project will not meet its 19-month deadline.

As per the civic body, if demolition of unauthorised structures, on either side of the bridge, is not taken up on an urgent basis by the two wards, the reconstruction will be delayed.

Central Railways (CR) demolished the Carnac Road over bridge (ROB) portion on November 20 last year and reconstruction of the entire ROB has not yet been executed by the BMC’s bridges department.

Repeated reminders by the bridges department to A ward in Fort and B ward in Dongri to remove the unauthorised structures — hutments, structures abutting the existing retaining wall of the bridge, encroachments, projections on existing road i.e., Lokmanya Tilak Marg — have not yielded desired results.

On the west of Carnac bridge is a jhunka bhakar kendra, a gymnasium, a Shiva temple, BEST substation and Pydhonie traffic police chowki.

On the east is another Pydhonie traffic police chowki, a Masjid toilet block, part portion of ROTA printing press, hutments, projections of footpath and on both sides of the bridge, there is shifting of water mains, old sewer mains and storm water drains, including BEST power cables.

According to the BMC, several structures at the site are proving to be a hindrance to the reconstruction of the bridge.

 
ABOUT THE AUTHOR
Leena Raghunath Baliga

Leena Raghunath Baliga (byline: Linah Baliga) is Associate Editor with nearly two decades of experience in journalism,and has earlier worked with TOI, DNA and Mumbai Mirror specialising in civic affairs, urban governance and political reporting. Based in Mumbai, she has looked into the functioning of civic administration, public policy and governance, with a particular focus on the Brihanmumbai Municipal Corporation (BMC), urban infrastructure, housing, redevelopment and city planning. Over the years, she has consistently reported on issues that directly impact citizens, including municipal administration, public health, BEST, environmental concerns, major infrastructure projects and state government policies affecting urban development. Her reporting combines on-ground reporting, making complex civic and governance issues accessible to readers while ensuring accountability in civic administration. She has extensively covered political developments that shape urban policy. Her work has also focused on redevelopment policies, affordable housing and the implementation of major infrastructure projects across Mumbai.She continues to chronicle the evolving and changing landscape of Asia's richest municipal corporation. When she isn't chasing stories or poring over civic documents, she enjoys dabbling in art and unwinding with music. An avid rock 'n' roll enthusiast, she has an anachronistic taste in music, with a playlist that happily skips across decades, filled with timeless classics.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Notifications

Get breaking alerts directly from the newsroom

Notifications are on!You'll be notified when news breaks