A Uttar Pradesh government-appointed committee has begun examining whether Suraksha Group is complying with the NCLT-approved resolution plan for Jaypee Wish Town in Sector 128, including the pace of construction, utilisation of funds collected from homebuyers and deployment of manpower, officials said on Wednesday.

The committee began a series of meetings with representatives of Suraksha Group and homebuyers on Oct 7. The meetings will continue on Oct 8 and Oct 9 and may be extended if required, officials said.
“We are investigating various issues to see whether the resolution plan approved by the NCLT is being fully complied with. We are assessing the actual progress of construction and whether funds received from homebuyers are being utilised for the purpose for which they were collected. We will also see if adequate manpower has been deployed to complete the work on time,” said Santosh Kumar, Noida authority’s officer on special duty, who heads the committee.
The state government constituted the five-member committee on September 11. Besides Kumar, it comprises two officials each from the planning and finance departments of the Noida and Yamuna authorities.
Wish Town homebuyers have alleged delays and irregularities in the construction and development of the project.
The back story
{{/usCountry}}Wish Town homebuyers have alleged delays and irregularities in the construction and development of the project.
The back story
{{/usCountry}}In February, the NCLT constituted a two-member fact-finding committee comprising former NCLT members Prasanta Kumar Mohanty and Deepti Mukesh. In its report submitted on August 20, the committee found delays in completion of the project.
According to the report, of the 250 residential towers planned by Jaypee Infratech Limited (JIL), 91 towers comprising 12,867 units had been completed before Suraksha took over the debt-ridden company.
The report said Suraksha was required to complete residual work on 62 other near-complete towers, comprising 6,067 units, within 18 months. However, more than two years later, 3,444 offers of possession had been issued and 2,614 sub-lease deeds executed. The committee said more than 6,000 offers of possession could have been issued by then.
In September, Suraksha Group promoter Sudhir Valia said the company had completed 84 of the 159 towers that were stalled when it took over JIL’s operations. The company also said it had handed over possession of 5,000 flats to homebuyers.
Ashish Mohan Gupta, president of JIL Real Estate Allottees Welfare Society (JREAWS), said the NCLT-appointed committee had upheld homebuyers’ complaints about delays.
“The NCLT committee has concluded that the grievances and allegations of delay in construction and delivery of flats raised by homebuyers are correct and genuine, and that Suraksha has failed to complete the projects as promised in the resolution plan, thereby breaching its obligations towards thousands of allottees,” Gupta said.
He said homebuyers were seeking project-wise and tower-wise deadlines for completion, particularly for stalled towers.
Also Read: NCLT approves Suraksha group’s plan to take over Jaypee Infratech