Bombay high court refuses to stay reclamation for mid-sea Shivaji memorial in Mumbai

NGO says eco nod invalid, HC accepts state’s stand on Centre’s authority to decide

Updated on: Nov 3, 2018, 09:53:44 IST
Hindustan Times | By
Prefer HTon Google
Advertisement

The Bombay high court (HC) on Friday refused to stay reclamation at the site of the proposed 212m-high Chhatrapati Shivaji Maharaj Memorial in the Arabian Sea, off the Mumbai coast, sought on the grounds that the “environment clearance granted to the project was invalid”.

An artist’s impression of the Chhatrapati Shivaji Memorial. (HT FILE)
An artist’s impression of the Chhatrapati Shivaji Memorial. (HT FILE)

City based non-government organisation Conservation Action Trust (CAT) claimed the ministry of environment and forest (MoEF), in 2015, changed the coastal regulatory zone rules to allow construction of monuments and memorials in CRZ-IV areas. The petition claimed the final notification on the change had a clause that empowered the Centre to exempt states from holding public hearings before grant of environmental clearance. This, the NGO claimed, was added to the final notification without first notifying it along with the 2014 public notice.

The petitioner argued that the clause required a separate order to be passed by the Centre granting exemption to the government from public hearings. As no such order was passed, the clearance for reclamation of land equivalent to two Oval Maidans became illegal, stated the petition, adding the situation would become irreversible, if the government was allowed to go ahead with the plan.

The bench also accepted the state’s stand that public hearing was not required to be held in case of the memorial, as no human habitation was affected by the project and no person was required to be rehabilitated or resettled.

“It also cannot be overlooked that the project is considered by the state government to be a project of national importance,” it said.

The state said it has obtained clearances and NOCs from 14 different authorities, and got specialised studies of the site conducted before giving the contract to L&T on June 20, 2018.

The work at the site began on October 19.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe