After complaints by buyers, DTCP seeks details of project, finances from OSB Developers

The department of town and country planning (DTCP) on Wednesday directed OSB Developers to share the status of the construction of its project OSB Golf Heights in Sector 69

Published on: Jun 2, 2022, 00:29:13 IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The department of town and country planning (DTCP) on Wednesday directed OSB Developers to share the status of the construction of its project OSB Golf Heights in Sector 69.

HT Image
HT Image

The DTCP also asked the developer to submit how much money it had so far received from its buyers and to look into why banks were refusing loans to allottees for the project.

“We have sought details of the buyers, payments made and other related issues. Also it has been decided that those buyers who have paid the developer only 5% of the money will be given 20 days to pay at least 20% more,” senior town planner Sanjeev Mann said.

The department issued the directions after a group of homebuyers, who bought units in the affordable project, complained that the pace of construction was slow and that’s why banks were refusing them loans to invest in the project.

“The project received environmental clearance in 2019 and despite that not more than 5% construction has taken place. Meanwhile, the developer is still demanding that we pay instalments regularly, and if we don’t the allotment will be cancelled,” alleged a buyer, requesting anonymity.

Chander Kant, another buyer, said that he had paid over 60% of the money, but despite that the developer was asking him to pay more while dodging the question of when the project would be ready.

Shyam Lal, a buyer, said that despite his good credit score, the bank refused him a loan, stating that the project was quite delayed. “We want the developer to resolve these issues,” he said.

After hearing the problems raised by buyers, Mann said that he called a meeting with promoters of the company next week to resolve buyers’ issues and to expedite construction.

A representative of the developer, meanwhile, said that project was slow to take off because only 275 units had been sold, and of these, 100 buyers had paid only 5% of amount. “We will share the details sought by the department in the next meeting,” he said.

  • Abhishek Behl
    ABOUT THE AUTHOR
    Abhishek Behl

    Abhishek Behl is a Special Correspondent with Hindustan Times, Gurugram bureau. With over a decade of experience in journalism, he reports on Gurugram's rapid urban transformation, covering the city's changing infrastructure, governance, and planning landscape. His reporting spans major civic agencies, such as the Gurugram Metropolitan Development Authority (GMDA), Department of Town and Country Planning (DTCP), Haryana Shahari Vikas Pradhikaran (HSVP), and the National Highways Authority of India (NHAI). Behl has reported on key urban development issues such as RRTS projects, metro expansion, road and highway projects, water supply, drainage, mobility, environmental concerns, land use planning, affordable housing, and the city's real estate sector. He closely tracks policy decisions, infrastructure implementation, and their impact on the city and its residents. He also covers regulatory action against illegal constructions, urban flooding, traffic management, and initiatives aimed at improving civic services and sustainable development. Behl has also written on political developments in south Haryana, focusing on elections and governance. His journalism is driven by fact-based reporting, ground-level coverage, and an understanding of the social and economic dynamics of Gurugram. Apart from work he is a cyclist and a cricketer and a resident of Palam Vihar since 2010.Read More