Gurugram targets 70,000 PNG connections in three months

The decision was taken at a high-level meeting attended by officials from the district administration, gas supply agencies, and civic bodies

Published on: Apr 01, 2026 07:24 AM IST
Advertisement

The district administration has set a target to provide piped natural gas (PNG) connections to nearly 70,000 households in Gurugram over the next three months, officials said during a review meeting chaired by the principal advisor for urban development on Tuesday.

Around 100 km of pipeline is planned, with existing network being expanded. Authorities said no subsidy is provided; costs vary by housing type. (PTI)
Around 100 km of pipeline is planned, with existing network being expanded. Authorities said no subsidy is provided; costs vary by housing type. (PTI)

The decision was taken at a high-level meeting attended by officials from the district administration, gas supply agencies, and civic bodies, with authorities prioritising expansion to ensure uninterrupted and safer domestic gas supply across Gurugram.

District food and supplies controller Ashok Rawat told HT that gas distribution companies, including Indraprastha Gas Limited (IGL) and Haryana City Gas, are scaling up infrastructure. “Efforts are being made to ensure that a large number of households are brought under PNG coverage within the stipulated timeline,” he said.

Officials said pipeline infrastructure is being expanded, with around 22,000 metres already available and additional work orders issued. Nearly 100 kilometres of pipeline is planned in the coming months. Around 60 teams are currently engaged in pipeline laying, with numbers expected to rise.

However, delays in approvals and coordination issues in some residential areas have slowed progress. Deputy commissioner Ajay Kumar said, “Applications for PNG pipeline work should be approved on priority so that the expansion work is not hindered.”

Sub-divisional magistrates have been tasked with resolving bottlenecks and coordinating with RWAs and local representatives. Residents in sectors including Sector 102 reported delays despite pipelines being laid, citing pending clearances. Officials said such issues are under review.

 
ABOUT THE AUTHOR
Leena Dhankhar

Leena Dhankhar is the Bureau Chief of the Gurugram bureau at Hindustan Times, where she covers crime, excise, civic agencies, forests and wildlife, real estate, and politics. With over a decade of experience at the organisation, she has reported some of the region’s most impactful stories, known for her deep investigative work and on-ground reporting. Leena has extensively covered major crime cases, systemic lapses and financial irregularities, often exposing civic agency failures and prompting administrative action. Her journalism is driven by accountability, public interest, and a commitment to highlighting issues that shape everyday life in Gurugram.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe