Decade after approval, KGMU’s 500-bed hostel awaits completion

KGMU spokesperson prof KK Singh said the university administration has issued three notices to the construction agency over repeated delays. He said the latest notice was served recently after the agency failed to meet earlier commitments. “If the hostel is not handed over by July 15, the university will submit a formal complaint to the government and initiate penalty proceedings against the agency,” he said.

Published on: May 16, 2026, 05:04:05 IST
Advertisement

The 500-bed hostel project of King George’s Medical University’s has remained incomplete nearly a decade after receiving approval in 2016, forcing around 100 super-specialty students to arrange accommodation outside the campus midway through the academic session.

The KGMU administration has warned the executing agency and set July 15 deadline for the completion of the project. (For representation)
The KGMU administration has warned the executing agency and set July 15 deadline for the completion of the project. (For representation)

At present, 86 DM and MCh students are staying in private paying guest accommodations and rented rooms as the hostel facility is yet to be handed over. The situation has particularly affected students coming from outside Lucknow, who are struggling to manage accommodation expenses alongside demanding medical training and hospital duties.

KGMU spokesperson prof KK Singh said the university administration has issued three notices to the construction agency over repeated delays. He said the latest notice was served recently after the agency failed to meet earlier commitments. “If the hostel is not handed over by July 15, the university will submit a formal complaint to the government and initiate penalty proceedings against the agency,” he said.

University officials said the proposal hostel was approved in 2016 and a revised budget was sent to the state government in May 2017. However, re-approval reportedly took nearly four years, followed by delays in administrative formalities and the tendering process.

The project cost has also risen sharply over the years — from the original estimate of ₹90 crore in 2016 to ₹157 crore at present.

 