State gives approval to Adani’s new transmission line

State government has given approvals to Adani Electricity Mumbai Infra Limited for the 1,000 MW HVDC Kudus-Aarey Transmission line project

Published on: May 16, 2022, 22:16:44 IST
Advertisement

Mumbai In a boost to Mumbai’s power security and the islanding system that insulates it from grid failures, the state government has cleared a major transmission project that will augment the capacity to wheel in additional power to the megapolis and decongest the transmission lines.

The project will cost an estimated  ₹7,000 crore, and is expected to be completed by 2026 (Praful Gangurde)
The project will cost an estimated ₹7,000 crore, and is expected to be completed by 2026 (Praful Gangurde)

It has given approvals to Adani Electricity Mumbai Infra Limited for the 1,000 MW HVDC Kudus-Aarey Transmission line project. The project will cost an estimated 7,000 crore, and is expected to be completed by 2026. At present, the city has a capacity to wheel in around 2,200 MW.

An Adani Electricity Mumbai Ltd spokesperson said, “The Kudus-Aarey HVDC Transmission line is a landmark project for strengthening Mumbai’s transmission system and will allow Adani Electricity to significantly leapfrog renewable energy supply to up to 60% of Mumbai’s demand.”

Work on designing the project, acquiring land and securing the statutory approvals is in progress.

The recent power outages in Mumbai have revealed the chinks in the islanding scheme introduced in 1981 to insulate the city from outages in the state grid. It has also pointed to the need to boost the capacity of transmission networks, which are getting clogged considering the growing demand for power.

Mumbai’s peak power has touched 3,850 MW this year and is expected to soar to 5,000 MW by 2024-25 and further to 6,000 MW by 2030. This demand is growing at an estimated 5 per cent per year, and any addition to the localised generation capacity is tough considering the space constraints and pollution control norms.

After the 2020 blackout in Mumbai, a state government committee noted that the city’s embedded generation capacity, which includes Tata Power’s 1,430 MW power plant and the 500 MW project of Adani Electricity (then Reliance Energy) at Dahanu was insufficient to meet the growing demand. Around 1,500 MW power was being brought to Mumbai through transmission corridors, which are already congested. The committee identified the need for augmenting the city’s transmission capacity.

The Maharashtra Electricity Regulatory Commission (MERC) identified two transmission projects, namely, the Kharghar-Vikhroli 400 kV scheme and the 1,000 MW Aarey-Kudus HVDC scheme. The Aarey-Kudus project was awarded to Reliance Energy, but the 80 km underground transmission line was delayed for various reasons. It was revived after the Adani group took over the Mumbai’s suburban power distribution business from Reliance Energy

The MERC granted a license to Adani Electricity Mumbai Infra Ltd. in 2021 to build the 1000 MW HVDC Aarey-Kudus Transmission line

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe