Virar-Dahanu railway expansion to commence in non-mangrove area

The Bombay high court has not granted permission for clearing about 24.5 hectares of mangroves in Palghar district for the project.

Published on: Jan 10, 2023 12:31 AM IST
By
Prefer HTon Google
Advertisement

Mumbai: Despite receiving Stage 1 (in principle) forest clearance (FC) in February 2022, the Mumbai Railway Vikas Corporation’s (MRVC) plans to enhance railway line capacity between Virar and Dahanu on the western line have not yet taken off, as the Bombay high court has not granted permission for clearing about 24.5 hectares of mangroves in Palghar district for the project. A writ petition before the HC is still pending in the matter.

Official documents show that the project will lead to the felling of 25,438 trees, including 24,302 mangroves. To offset the loss, compensatory afforestation has been proposed on 54 hectares of degraded land in three nearby villages in Palghar itself. (HT Photo)
Official documents show that the project will lead to the felling of 25,438 trees, including 24,302 mangroves. To offset the loss, compensatory afforestation has been proposed on 54 hectares of degraded land in three nearby villages in Palghar itself. (HT Photo)

However, the regional empowered committee (REC) of the ministry of environment, forests and climate change has allowed MRVC to start work on portions of the railway line that lie outside of the protected mangrove patches (about two hectares of land), while recommending the project for Stage II clearance, which is the final level of FC required for any project. With the Maharashtra Coastal Zone Management Authority having accorded the project CRZ clearance in November 2022, officials say that the HC’s pending permission is all that stands in the way of the project’s construction, slated for completion by 2025.

The project is part of Phase III of the Mumbai Urban Transport Project, and involves the laying of the third and fourth railway lines parallel to the existing double line corridor between Virar and Dahanu for a distance of about 63 km. “As the existing double-line corridor is oversaturated, it is not possible to increase the number of suburban services in this section,” an official from MRVC said.

Official documents show that the project will lead to the felling of 25,438 trees, including 24,302 mangroves. To offset the loss, compensatory afforestation has been proposed on 54 hectares of degraded land in three nearby villages in Palghar itself. From the two-odd hectares of land outside the mangrove area –where work will be carried out without needing the HC’s approval – a total of 200 trees will be transplanted within one year of receiving Stage II clearance. “We will carry out the work in the monsoon season and send a report to the REC,” said the official.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe