Noida authority orders test of steel in skywalk, drain projects

NOIDA: The Noida authority said on Sunday to have ordered quality tests on steel being used in the under-construction Sector 51-52 skywalk, and an RCC drain between sectors 50 and 51

Updated on: Aug 10, 2026, 08:18:32 IST
Advertisement

NOIDA: The Noida authority said on Sunday to have ordered quality tests on steel being used in the under-construction Sector 51-52 skywalk, and an RCC drain between sectors 50 and 51.

The move came after an inspection found alleged sub-standard steel being used at the two sites, said officials. (HT Archive)
The move came after an inspection found alleged sub-standard steel being used at the two sites, said officials. (HT Archive)

The move came after an inspection found alleged sub-standard steel being used at the two sites, said officials.

“The Authority will take harsh action against the contractors if the steel fails to meet prescribed quality standards. The concerned manager has also been asked to submit an explanation regarding the use of the material. After the reports the Authority will take appropriate action,” said S P Singh, general manager, Noida authority, in a media statement.

The Authority’s technical audit cell has collected steel samples from both projects and will get them tested by specialised institutions such as IIT Delhi, IIT Roorkee or Shriram Institute for Industrial Research, Delhi, said officials, adding that the payments to the contractors have also been ordered to be withheld until the test reports are received.

Notably, the Sector 51-52 skywalk, whose main elevated structure is largely ready, has been facing delays over an obstruction at the entry point near the Sector 51 Metro station. A beam at the station is blocking access, prompting the Authority to modify and extend the skywalk by around 100 metres.

Officials have said the extension is expected to make the facility operational within a month.

The L-shaped, air-conditioned skywalk, equipped with travelators, was launched in March 2023 with a one-year completion target. The project subsequently faced several hurdles, including construction restrictions imposed by the National Green Tribunal during winter, said officials.

The design was also changed after an underground metro cable was discovered during excavation, they said, adding that the structure was initially planned on single pillars but was redesigned with a two-column support system.

 
ABOUT THE AUTHOR
Vinod Rajput

Vinod Rajput writes on environment, infrastructure, real estate and government policies in Noida and Greater Noida. He has reported on environment and infrastructure in Delhi, Gurgaon and Panchkula in the past.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe