RRTS project: Duhai depot functional, to handle train operations for 82km project

This depot is the first one that has come up for the RRTS project, which will connect Delhi, Ghaziabad and Meerut with high-speed state-of-the-art trains

Updated on: Mar 07, 2023 12:19 AM IST
Advertisement

The Duhai Depot of the Delhi-Ghaziabad-Meerut Regional Rapid Transit System (RRTS) corridor is now functional with state-of-the-art facilities, National Capital Region transport corporation (NCRTC) officials said on Monday.

Officials said the depot will also have entry and exit points for passengers and will be used as an RRTS station. (Sakib Ali/HT Photo)
Officials said the depot will also have entry and exit points for passengers and will be used as an RRTS station. (Sakib Ali/HT Photo)

This depot is the first one that has come up for the RRTS project, which will connect Delhi, Ghaziabad and Meerut with high-speed state-of-the-art trains.

“The Duhai depot has many features such as controlling RRTS train operations in Delhi, Ghaziabad and Meerut. This depot will handle all such train operations till the second depot comes up at Modipuram in Meerut in March 2025. Besides these two depots, a stabling yard is also scheduled to come up at Jungpura in Delhi,” said Puneet Vats, chief public relations officer of NCRTC.

A 17km stretch of the RRTS project in Ghaziabad, known as the priority section, is likely to start operations this month. The Duhai Depot is one of the facilities that has been developed as part of five stations on the priority section.

The Duhai depot has administration buildings, workshops and inspection bay lines, which have been created in less than two years. A state-of-art facility for RRTS trainsets is also functional.

Officials said the depot will also have entry and exit points for passengers and will be used as an RRTS station. “The command-and-control centre will become fully operational once it is integrated with signalling. The Duhai depot will also handle train operations on the priority section,” Vats said.

The 17km priority section from Sahibabad to Duhai is getting ready for fully integrated trial runs, which will make way for passenger operations later. At present, NCRTC is conducting test runs of RRTS trains from the Duhai depot.

The entire 82km RRTS project, worth 30,274crore, is likely to become operational in March 2025.

 
ABOUT THE AUTHOR
Peeyush Khandelwal

Peeyush Khandelwal writes on a range of issues in western Uttar Pradesh – from crime, to development authorities and from infrastructure to transport. Based in Ghaziabad, he has been a journalist for almost a decade.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe