Bhairon Marg underpass: Railway NOC received, completion target December

Delhi government gets NOC from Indian Railways for Bhairon Marg underpass, aiming to complete it by December 2026, easing traffic congestion.

Published on: Apr 7, 2026, 04:00:14 IST
Advertisement

The Delhi government has received a no-objection certificate (NOC) from the Indian Railways for executing the remaining work for the development of the Bhairon Marg underpass – the final remaining project from the Pragati Maidan Integrated Corridor Project aimed at easing congestion on Ring Road and Bhairon Marg, officials said on Monday.

The project had been stuck for years due to pending clearances and lack of coordination, said PWD minister. (HT archive)
The project had been stuck for years due to pending clearances and lack of coordination, said PWD minister. (HT archive)

Construction work is now likely to resume, with a target of completing the remaining work by December 2026, Public Works Department (PWD) minister Parvesh Verma said.

“This project had been stuck for years due to pending clearances and lack of coordination. We approached it with a clear intent – to resolve issues, not to pass responsibility. With this NOC, the final hurdle has been cleared. The focus now is on execution, speed, and accountability. This project will be completed by December 2026,” Verma said.

While the main tunnel and five underpasses were inaugurated and opened to the public in June 2022 by Prime Minister Narendra Modi, Underpass No. 5 along Bhairon Marg remains incomplete. The project has been stuck since mid-2023, when construction had to be halted following the sinking and shifting of two concrete boxes being pushed under an active railway overbridge, PWD officials aware of the project details said.

The first major breakthrough came in August 2025, when the Union ministry of housing and urban affairs (MoHUA) approved a revised execution plan. That approval addressed core technical concerns, particularly soil settlement beneath the structure and the need for design modifications near the railway embankment.

“Even after MoHUA’s approval, the project could not move forward due to the absence of final clearance from Railways, given the proximity of the structure to active railway infrastructure. This remained the last and most crucial hurdle,” one of the officials cited above explained.

Verma said the underpass is a vital component of Delhi’s broader infrastructure network. “Once operational, it will ease congestion around Pragati Maidan and the ITO corridor, improve east-central connectivity, and ensure smoother traffic flow during major national and international events hosted at the ITPO complex.”

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe