BMC imposes penalty of 50.53 lakh on road contractors for delaying repairs

The civic body has instructed contractors to use additional manpower and work around the clock to fix potholes promptly once the rains subside

Updated on: Jul 27, 2024, 08:58:43 IST
Advertisement

Mumbai: After days of incessant, heavy rains left the city’s roads peppered with potholes, the Brihanmumbai Municipal Corporation (BMC) has penalised its contractors a total of 50.53 lakh for delaying repair and maintenance work during the monsoon.

Mumbai, India - July 26, 2024: BMC works filling pothole in the eastern express Highway near Ghatkopar in Mumbai, India, on Friday, July 26, 2024. (Photo by Satish Bate/ Hindustan Times) (Hindustan Times)
Mumbai, India - July 26, 2024: BMC works filling pothole in the eastern express Highway near Ghatkopar in Mumbai, India, on Friday, July 26, 2024. (Photo by Satish Bate/ Hindustan Times) (Hindustan Times)

The civic body has instructed contractors to use additional manpower and work around the clock to fix potholes promptly once the rains subside. Municipal commissioner Bhushan Gagrani has warned the contractors that failing to follow these instructions will result in punitive action.

After the July 8 deluge, which saw parts of Mumbai receive over 300mm of rain within six hours, the BMC had directed engineers in each of its 227 wards to take proactive measures in identifying and repairing potholes. A deputy engineer has to conduct daily inspections of roads in their ward and ensure any potholes are promptly filled with mastic. However, contractors have been failing to complete repairs on time during the monsoon, the BMC said.

As a result, penalties totalling 50.53 lakh have been imposed on various contractors for the period of June 1 to July 25. This includes 28.30 lakh for pothole-filling contractors, 20.45 lakh for project contractors, and 1.18 lakh for liability period contractors. The fines will be deducted from the contractors’ fees.

The BMC has instructed its engineers to remain vigilant after a spell of rain and conduct daily inspections. Pre-monsoon meetings emphasised the need for early detection and mastic repairs to address potholes. Contractors were warned that delays in road repairs will not be tolerated, said Bangar.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe