Next Story

Posco land takeover to resume tomorrow

The protest against Posco steel plant in Orissa intensified today as authorities set to resume land acquisition for its $12 billion project from tomorrow.

Updated on: Jun 17, 2011, 16:43:33 IST
IANS | By , Bhubaneswar
Prefer HTon Google
Advertisement

The protest against Posco steel plant in Orissa intensified on Friday as authorities set to resume land acquisition for its $12 billion project from Saturday.

HT Image
HT Image

The villagers, including women and children, continued their demonstration at troubled Govindpur village in coastal Jagatsinghpur district to prevent entry of officials to the site.

"More than 2,000 villagers created a human barricade," Prasant Paikray, anti-Posco agitation leader, told IANS.

The protest will continue till the government withdraws the project from the area, he added.

He also accused the officials of forcibly acquiring lands from the villagers.

The movement against the project has received a boost with political parties extending their support to the villagers.

Protesting the forcible land acquisition, hundreds of activists of the Communist Party of India (CPI), the Communist Party of India-Marxist (CPI-M), the Forward Bloc, the Rashtriya Janata Dal, the Samajwadi Party and Ekta Parishad staged a demonstration in Bhubaneswar Friday against the project.

The state's main opposition Congress and the Bharatiya Janata Party (BJP) also said they will send their senior leaders to the area to make an assessment of the ground situation.

The land acquisition was earlier stopped for four days due to a local festival.

"We were preparing to resume the land acquisition today (Friday), but had to cancel it due to rains," additional district magistrate SK Chaudhuri told IANS.

"If the weather remains conducive, we will start the process again from tomorrow (Saturday)," he said.

Posco has planned to built a 12 million tonnes steel plant - the largest foreign investment in India - near the port town of Paradip, about 120 km from Bhubaneswar.

The company requires about 4,004 acres of land for the project, of which 2,900 acres is forest land.

The local administration said it has already acquired nearly half of the land required for the project.

 
Get the latest India News, breaking headlines and real-time updates from across the country. Stay informed about politics, government policies, crime, weather and major national developments.
Get the latest India News, breaking headlines and real-time updates from across the country. Stay informed about politics, government policies, crime, weather and major national developments.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe