Tunnel boring for Mumbai coastal road project to begin on October 25

The Brihanmumbai Municipal Corporation (BMC) will begin the tunnel boring work for the Mumbai Coastal Road Project by October 25, the timeline prepared by the civic

Published on: Sep 8, 2020, 01:22:36 IST
By
Prefer HTon Google
Advertisement

The Brihanmumbai Municipal Corporation (BMC) will begin the tunnel boring work for the Mumbai Coastal Road Project by October 25, the timeline prepared by the civic coastal road department stated. Following the commencement of the work, it will take eight to 10 months to complete the boring through the 3.4-kilometre (km)-long twin tunnels between Priyadarshini Park at Malabar Hill and Girgaum Chowpatty.

HT Image
HT Image

BMC has completed about 16% of the work for the Coastal Road Project, and has set a deadline of July 2023 to complete the entire project, a senior civic officer from the department said.

The civic body is now re-assembling the parts of the tunnel boring machine (TBM) it purchased from China last year at the work site in Priyadarshini Park. The machine arrived in April, and was taken to the site in many dismantled parts in 17 trailer trucks.

The TBM will drill the 3.4-km-long twin tunnels partially running under the sea, between Girgaum and Malabar Hill, as part of the 9.98-km-long Coastal Road between Priyadarshini Park, and the Worli end of the Bandra Worli Sea Link. As there will be two parallel tunnels of 3.4-km length each, the total length of the tunnels will be 6.8 km. They will run 25 metres below the surface at Girgaum and 75 metres below the surface at Malabar Hill. The width of each tunnel will be 12 metres, with two lanes – each 3-3.2 metres wide – one emergency lane.

As per BMC’s original estimate, the TBM is to complete the tunnel boring work in 276 days. As the machine will be able to drill through a minimum of 3 metres each day, it will need roughly 276 days to complete the entire planned length of the tunnel.

While expertise from the manufacturer will be required at the time of boring, BMC is in a fix now owing to the ongoing tensions with China.

Another civic official said, “Chinese experts who are already working on the Mumbai Metro project and the Bengaluru Metro project will help the civic body with this work. Besides, the general consultant for the coastal road project, AECOM, has experts on its panel who will be called to help the civic body.”

Earlier, BMC aimed to complete the coastal road by 2022. However, the Bombay high court put a stay on the work, which was later lifted by the Supreme Court. Following this, work resumed on December 18 last year after 154 days.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Notifications

Get breaking alerts directly from the newsroom

Notifications are on!You'll be notified when news breaks