Why has Byculla zoo revamp been delayed? Mumbai civic body sends letters, not emails

Mumbai civic officials said it may take six more months before Phase II of the project begins

Updated on: Oct 9, 2017, 13:43:46 IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

The Brihanmumbai Municipal Corporation’s (BMC) failure to keep up with the digital age has led to the Byculla zoo revamp being delayed. Despite having email at its disposal, the civic body is still using postal mail to verify the credentials of bidders for Phase II of the project.

Phase II of the zoo project includes the construction of 17 animal enclosures for Asiatic lions, Bengal tigers, sloth bears and jackals. (HT File)
Phase II of the zoo project includes the construction of 17 animal enclosures for Asiatic lions, Bengal tigers, sloth bears and jackals. (HT File)

Civic officials said it may take six more months before Phase II can begin. This phase includes the construction of 17 animal enclosures for Asiatic lions, Bengal tigers, sloth bears and jackals. In August, bidders who applied for the Rs120 crore contract of Phase II submitted certificates of their work experience with certain private and government bodies. The BMC then sent letters to these firms based in Uttar Pradesh, Rajasthan, Goa, and even Oman, to verify the contractor’s credentials.

“Four bidders applied and we are verifying 20 to 22 certificates. However, the bidders did not submit the contact numbers or email addresses of the parties they previously worked for. We only have their addresses, so we send speed posts. We have to wait till we get a reply confirming their credentials, only then can we move ahead and award the contracts,” said a civic official, who did not wish to be identified.

This time, the BMC has decided to verify the credentials of all bidders. It usually verifies only the lowest bidder, in case of tenders for other civic works

Civic officials said the BMC has asked all applicants to submit Rs500 and an undertaking, saying the contractor will bear the cost of the Goods and Services Tax (GST) over and above the final cost of tender. Some are unwilling to do so, which has led to further delays, sources said.

“It is so simple to do a basic internet search and find the party’s phone number or email address. Besides, there are options such as Skype, which let you video call. Verifying documents should be simpler. At the end of the day, Mumbaiites stand to lose out if the zoo revamp is delayed,” said activist Rishi Agarwal.

 
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Notifications

Get breaking alerts directly from the newsroom

Notifications are on!You'll be notified when news breaks