In spite of Rs 10 crore grant,canal rehabilitation hangs fire

Work on the rehabilitation project of 800-km Bist-Doab canal continues to hang fire nearly a year after its scheduled start date of October 1, 2013, even after the National Bank for Agriculture and Rural Development (Nabard) sanctioned Rs10 crore for the project in March this year.

Updated on: Aug 21, 2014, 00:21:33 IST
Advertisement

Work on the rehabilitation project of 800-km Bist-Doab canal continues to hang fire nearly a year after its scheduled start date of October 1, 2013, even after the National Bank for Agriculture and Rural Development (Nabard) sanctioned Rs10 crore for the project in March this year.

HT Image
HT Image

Previously, the state government had failed to arrange funds and since March there have been several reasons cited for not starting work.

Even as Nabard sanctioned the money, officials claimed to have all their attention consumed by the general elections.
After the elections, it was now claimed that the paddy sowing season was to begin and thus the irrigation department had to release water into canal, which runs for around 800 km in the state and has a capacity to irrigate more than 4.92-lakh-acres agriculture land.

A senior official of the irrigation department, not wishing to be named, said: "We did not start work on the project as most of distributaries of the 800-km
Bist-Doab canal had not been cleaned. As a result, water failed to reach the fields adding to the misery of farmers caused by a weak monsoon."
He added that the government had been facing criticism for several years for "ignoring" the canal, which was the main source of irrigation in the four districts of Doaba region - Jalandhar, Nawanshahr, Kapurthala and Hoshiarpur.

Irrigation secretary Kahan Singh Pannu said that he had no knowledge of the project. "Please contact chief engineer (canals) Amarjit Singh," he said. Singh again could not be contacted.
Finally, irrigation department executive engineer Arwinder Singh Sohal said that Rs 10 crore had been released by Nabard and work on the project will start after the paddy season ends in October this year.

 
ABOUT THE AUTHOR
Jatinder Kohli

Jatinder Kohli is a senior correspondent at Jalandhar. He covers crime and health, besides Nawanshahr district.

SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe