Sign in

Project delay caused ‘mental agony’: TN RERA orders developer to pay ₹3 lakh to buyer

Chennai real estate: TN RERA orders builder to pay 3 lakh compensation to homebuyer for ‘mental agony’ over delayed possession

Published on: Mar 10, 2026 11:22 AM IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

The Tamil Nadu Real Estate Regulatory Authority (TN RERA) directed a developer to compensate a homebuyer for prolonged delays in completing a project, noting that the delay caused significant ‘mental distress’. The regulator ordered the builder to pay 3 lakh in compensation to the homebuyer for the hardship caused by the delayed possession.

The Tamil Nadu Real Estate Regulatory Authority directed a developer to pay  ₹3 lakh to a homebuyer for prolonged project delays that caused “mental agony.”(Photo for representational purposes only) (Souptik Datta )
The Tamil Nadu Real Estate Regulatory Authority directed a developer to pay ₹3 lakh to a homebuyer for prolonged project delays that caused “mental agony.”(Photo for representational purposes only) (Souptik Datta )

“The complainants had to undergo considerable mental agony due to the respondent’s failure to complete the project, hand over the property and register the relevant documents on time,” the order said.

“In the result, it is ordered that the respondent should pay a compensation of 3,00,000 to the complainants for mental agony, distress and suffering and also 50,000 for legal expenses,” the order said.

The case

The homebuyers booked an apartment in the Casagrand Millenia project in July 2022, paying a booking advance of 1 lakh. The total cost of the apartment was 2.11 crore. They later entered into a sale agreement and construction agreement with the developer in September 2022, with a handover date of June 2023, the order said.

“But contrary to the promise of the respondent to handover the unit by June 2023, the completion and delivery of the apartment was extended to March 2024 instead of December 2023. But till now, the completion and handing over did not happen. In the meantime, the complainants have paid 1.92 crore, leaving a balance of 17.6 lakh to be paid by the bank. Thus, the respondent had received almost 91% of the sale value of the subject unit,” the order said.

TN RERA noted that in July 2023, the developer issued a termination notice cancelling the allotment, citing overdue payments and stating that it would retain 20% of the booking amount while refunding the balance.

“The complainants had to face a lot of mental agony and distress due to the failure on the part of the respondent by delaying the completion, handing over and registration of relevant documents,” the order said.

Also Read: Karnataka RERA pulls up Bengaluru real estate developer for not constructing compound wall, misusing undivided share

Developer refutes claim

The developer told the authority that the complaint was not maintainable and claimed that the buyers had defaulted on scheduled payments.

“The project was properly developed after securing statutory approvals and legal compliance as applicable for the development. The construction agreement was entered into in December 2022, with a sale agreement for the UDS also. The construction agreement clearly states that the apartment would be delivered by December 2023, with a grace period which was acknowledged and signed by the complainants. The complainants continuously defaulted on making the scheduled payments. Still, there is a balance of 32.1 lakh payable by the complainants,” the developer said.

Also Read: Karnataka RERA pulls up Bengaluru builder for not transferring khata to homebuyer, directs action within 30 days

RERA order

After examining the agreements, payment records and email communications between the parties, the authority observed that the developer had failed to hand over the apartment within the agreed timeline.

“The respondent had undertaken to complete the construction of the apartment by December 2023, with three-months grace period. So, the undertaking period would expire by March 2024, and the respondent is bound to complete the construction and deliver possession of the apartment to the complainants,” TN RERA said.

“The last three payments were made even before the filing of the counter-statement of the respondent side. It shows that even before 12.03.2025, the date of filing of the counter statement, the complainants had been prompt in making the payments, which is not disclosed by the respondent,” it said.

“The total cost of the subject unit is 2.10 crore, and the complainants had already paid 1.92 crore even by August 2023, upon availing a home loan only for the purpose of purchasing the apartment. Thus, they have paid more than 91% of the cost of the apartment,” TNRERA said.

There was no evidence showing that the developer issued regular reminders to the buyers regarding the alleged outstanding balance. The authority also observed that it was neither fair nor justified for the developer to retain a substantial portion of the construction cost between 2022 and 2023 and then abruptly issue a termination notice.

“In these circumstances, the delay caused by the respondent is not acceptable and thereby the complainants are entitled to a compensation of 3,00,000 towards the mental agony they have sustained due to the delay,” TN RERA said.

A list of questions has been sent to the developer. The story will be updated once a response is received.

  • Souptik Datta
    ABOUT THE AUTHOR
    Souptik Datta

    Souptik Datta is a deputy chief content producer at Hindustan Times Digital, where he reports on southern India with a focus on real estate, urban infrastructure and environmental urban issues. His coverage tracks the intersection of policy, capital flows, regulation and sustainability, examining how these forces shape housing markets, commercial real estate and large-scale infrastructure development across rapidly transforming cities. He also closely tracks civic issues affecting urban residents, including property taxation, planning approvals, public transport expansion, water stress, waste management and the governance challenges that influence everyday life in India’s metros. Souptik’s reporting is driven by a strong interest in accountability, consumer rights and the lived realities of homebuyers and investors navigating volatile pricing cycles, regulatory changes and project delivery risks. He frequently analyses project launches, land monetisation strategies, planning frameworks, RERA-related developments and the broader implications of infrastructure investments on emerging growth corridors. His work blends on-ground reporting with data-backed analysis and long-form explainers aimed at demystifying complex real estate and infrastructure developments for readers. He is an alumnus of the Indian Institute of Journalism and New Media. Before joining Hindustan Times Digital, Souptik was associated with Moneycontrol at Network 18, where he covered real estate, infrastructure and allied sectors, producing market insights, policy-led stories and in-depth features. Outside the newsroom, Souptik is an avid solo traveller and documentary enthusiast, exploring diverse regions and visually documenting unique narratives through film and photography. In his early career, Souptik also freelanced as a documentary photographer, independently working on visual storytelling projects that captured grassroots narratives, urban change and everyday life. He can be reached at souptik.datta@htdigital.in.Read More

Stay updated with latest Real Estate news and updates from India and around the World, explore the latest market moves and premium property listings updates now on Hindustan Times