Greenfield Project: NHAI approves four-fold increase in compensation for landowners

Landowners who were earlier being offered around ₹24 crore will now get around a crore; work on the project is expected to begin within a month

Published on: May 4, 2022, 01:35:47 IST
Advertisement

Work on the much-awaited Greenfield Project, aimed at decongesting the Airport Road in Mohali, is finally expected to begin within a month as the National Highway Authority of India (NHAI) has approved four-fold increase in the compensation amount for landowners. The project had been put on hold for nearly eight months as landowners were protesting against the rates being offered for their land.

NHAI had come up with the Greenfield Project after scrapping the 40-km Kharar-Banur-Tepla road project in July 2019, owing to its high cost. (HT File)
NHAI had come up with the Greenfield Project after scrapping the 40-km Kharar-Banur-Tepla road project in July 2019, owing to its high cost. (HT File)

While earlier, the NHAI was to pay between 24 lakh and 4.12 crore per acre, depending on the location, now they have approved compensation of 1 crore and 1.09 crore per acre to those who were to get 24 lakh per acre.

Mohali district revenue officer (DRO) Gurdev Singh said, “NHAI has approved revised rates for compensation and we have got a letter in this regard. In villages where the compensation rate was around 24 lakh per acre, the administration has revised the rate to more than a crore.”

A senior NHAI official, privy to the development, said, “Now since the rates have been revised, we want all landowners to come forward and take their compensation which is already lying with the department. Once the money is disbursed, we will start the work on the project within a month’s time.”

700 crore project

NHAI had come up with the Greenfield Project after scrapping the 40-km Kharar-Banur-Tepla road project in July 2019, owing to its high cost. The 32-kilometre road, from IT Chowk (PR-7) near Chandigarh International Airport to Kurali-Chandigarh road, is being constructed at a cost of 700 crore. Once complete, it will help ease traffic in Chandigarh and Zirakpur by serving as an alternative route for those from Delhi heading towards Himachal Pradesh and Jammu & Kashmir.

With the project on hold since September last year, Member of Parliament Manish Tewari had recently taken up the matter with Union transport minister Nitin Gadkari and urged him to expedite the project as it will help in decongesting the traffic of Mohali. The greenfield road is built in an area that has never been developed.

 
ABOUT THE AUTHOR
Hillary Victor

Hillary Victor is a Special Correspondent at Chandigarh. He covers Chandigarh administration, municipal corporation and all political parties.