Centre clears final stretch of Pragati Maidan corridor, work to resume after year-long halt

The main tunnel and five of the six underpasses in the Pragati Maidan corridor became operational two years ago to improve connectivity between Ring Road, Bhairon Marg, and Mathura Road. Underpass 5 remains the missing link: a 110-metre stretch connecting Bhairon Marg to Ring Road

Published on: Aug 5, 2025, 05:46:06 IST
Advertisement

The Union ministry of housing and urban affairs (MoHUA) has granted approval to resume work on the Bhairon Marg underpass—Underpass No. 5—the final piece of the Pragati Maidan Integrated Transit Corridor project.

Work on the underpass had stalled in 2023 after flooding from the Yamuna caused structural damage to the site. (PTI)
Work on the underpass had stalled in 2023 after flooding from the Yamuna caused structural damage to the site. (PTI)

The underpass is crucial for completing the loop of the corridor and alleviating chronic traffic snarls near Bhairon Marg and Ring Road. Work on the underpass had stalled in 2023 after flooding from the Yamuna caused structural damage to the site. In response, the public works department (PWD) prepared a revised action plan, which has now received clearance from the central government.

In its communication, MoHUA endorsed several critical steps proposed by PWD to revive and complete the project. These include immediate grouting under the box structures to stabilise soil and prevent further settlement, stitching of boxes beneath the railway embankment to strengthen the track and ensure structural safety, and adopting a cast-in-situ construction method with revised height parameters deemed most feasible in the current scenario.

PWD minister Parvesh Verma welcomed the clearance, calling it a step towards transparency and accountability. “Every rupee spent on infrastructure must yield public value, and I am glad this solution protects both engineering integrity and financial responsibility. We thank MoHUA for their support. Execution is now our priority—delay is not an option,” he said.

Verma visited the project site on July 7. An official from his office said PWD has been instructed to start the approved work immediately and submit weekly progress reports. “The project will be completed within the previously sanctioned budget,” the official added.

The main tunnel and five of the six underpasses in the Pragati Maidan corridor became operational two years ago to improve connectivity between Ring Road, Bhairon Marg, and Mathura Road. Underpass 5 remains the missing link: a 110-metre stretch connecting Bhairon Marg to Ring Road. Of this, 82 metres have already been completed, including a two-lane carriageway from ITO to Bhairon Marg. The remaining 28 metres—located under a railway embankment—was where construction had stalled.

Following the setback, PWD enlisted experts from IIT-Delhi, IIT-Bombay and the Central Building Research Institute (CBRI) to carry out a technical evaluation. Based on their recommendations, the underpass design was scaled down. “The original three-lane design with a 5.5-metre clearance will now be replaced with a two-lane underpass, 3.9 metres in height and 6.25 metres in width, suitable only for light motor vehicles,” said a senior PWD official.

Once completed, the underpass will re-establish a vital directional link between Bhairon Marg and Ring Road, relieving one of central Delhi’s most clogged traffic points. The PWD also plans to install digital signage and height barriers to restrict the entry of heavy vehicles.

 
ABOUT THE AUTHOR
Paras Singh

Paras Singh is a New Delhi-based journalist with Hindustan Times, where he serves as Deputy Metro Editor. He reports on urban governance, the Delhi government, the Delhi BJP, water management, the environment, communities and city life. He joined Hindustan Times in 2021 after beginning his journalism career at The Times of India in 2016, where he covered civic bodies, the water and power sectors, and urban infrastructure. Over the last decade, some of his reporting has led to significant public impact, with investigations into environmental violations, corruption and illegal industrial activity contributing to multiple judicial interventions by the National Green Tribunal and the Delhi High Court. A graduate of St. Stephen's College, University of Delhi, Paras studied journalism from the Indian Institute of Mass Communication (IIMC), New Delhi. Having extensively covered the capital's evolving civic and governance landscape, his recent work increasingly explores Delhi's history, built heritage, urban evolution and the relationship between people and place, alongside continuing to report on governance and public policy.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!

Stay updated with all top Cities including, Bengaluru, Delhi, Mumbai and more across India. Stay informed on the latest happenings in World News along with Delhi Election 2025 and Delhi Election Result 2025 Live, New Delhi Election Result Live, Kalkaji Election Result Live at Hindustan Times.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe