A team from Greater Noida authority and Noida traffic police inspected the underpass site to assess pre-project tasks such as removing encroachments and relocating electric poles and trees
Key underpass beneath Dwarka Expressway in Gurugram opened for trial, connecting Basai overbridge with Sectors 102 and 102A. Residents to benefit from improved traffic flow.
Nearly 95% of construction work of the underpass has been completed and the road is being built at a cost of ₹24 crore. It is 584 metres in length and has four lanes to facilitate the movement of traffic on both sides
According to the project’s progress report for the month of March, land acquisition from the Irrigation and Flood Control department has delayed the work further