2.49cr payment by MCG over planned parking raised in audit

Documents show the contractor received mobilisation advance in January 2020 though the civic body did not yet possess the land required for construction.

Published on: Mar 11, 2026 06:17 AM IST
Advertisement

A planned multilevel parking project near the Sadar Bazar Post Office is under lens, over a payment of 2.49 crore made by the Municipal Corporation of Gurugram (MCG) to the contractor as “mobilisation advance” in January 2020, despite not having possession of land for the project, according to official documents accessed by HT. Six years since the award, delays in land transfer and administrative lapses have stalled the project.

Officials say an inquiry may be initiated and the tender could be cancelled as the project remains stalled due to delays in land transfer. (HT)
Officials say an inquiry may be initiated and the tender could be cancelled as the project remains stalled due to delays in land transfer. (HT)

A senior MCG official, requesting anonymity, said that with 2.49 crore of public funds lying with a private contractor for nearly six years despite no construction on ground, an inquiry will be initiated and the tender may be cancelled.

A retired superintending engineer from the Public Works Department (PWD), requesting anonymity, said the case required examination of whether the mobilisation advance was provided with a bank guarantee. “Such advances are usually given with bank guarantees and interest conditions. If 2.5 crore remained idle for six years, its value with interest could reach 6–7 crore. Normally, if work does not start within six to eight months after a work order, the contract is cancelled,” the retired official said.

The contractor did not respond to multiple requests for comment.

The MCG did not comment when questioned about interest accrued from the payment, but sought to clarify that the land transfer will be resolved and work will be initiated.

“The process of purchasing the land for the multilevel parking near the post office has been completed and the possession will soon be taken by the revenue branch of the corporation. The contractor has agreed to carry out the construction. If the work is not executed, the amount paid will be recovered and the project will be re-tendered,” said Sandeep Dhundhwal, executive engineer, MCG.

The project is estimated to cost 49.03 crore in all.

Officials said the project site is spread across 3,700 square yards and that the municipal corporation has already deposited 43.66 crore for acquiring the land, and an additional 17 lakh has been paid to the Public Works Department (PWD) for demolishing an old structure at the site. However, the process of formally transferring the land from the PWD to the corporation is still pending.

The prolonged delay has also raised questions about why the contract was awarded and payment made before completing land-related formalities. Experts said such lapses can lead to financial losses and project delays.

 
ABOUT THE AUTHOR
Leena Dhankhar

Leena Dhankhar is the Bureau Chief of the Gurugram bureau at Hindustan Times, where she covers crime, excise, civic agencies, forests and wildlife, real estate, and politics. With over a decade of experience at the organisation, she has reported some of the region’s most impactful stories, known for her deep investigative work and on-ground reporting. Leena has extensively covered major crime cases, systemic lapses and financial irregularities, often exposing civic agency failures and prompting administrative action. Her journalism is driven by accountability, public interest, and a commitment to highlighting issues that shape everyday life in Gurugram.

Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!.

Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe