Mohali: Builder to pay 44 lakh for late flat delivery

The Punjab Real Estate Regulatory Authority ordered issuance of a Debt Recovery Certificate if Omaxe fails to pay within 90 days

Published on: Nov 26, 2025 08:24 AM IST
By , Mohali
Prefer HTon Google
Advertisement

The Punjab Real Estate Regulatory Authority (RERA) has directed Omaxe Chandigarh Extension Developers Pvt Ltd to pay 44.63 lakh to a couple for not delivering their flat on time.

Penalising the developer, the authority directed that  ₹44.63 lakh be paid to the couple as interest. (HT Photo)
Penalising the developer, the authority directed that ₹44.63 lakh be paid to the couple as interest. (HT Photo)

The couple, Anil Kumar Sanghi and Sunita Sanghi, both former bureaucrats, had booked a flat at The Lake project in New Chandigarh by paying 76.47 lakh in 2015, their counsel M Shahnawaz Khan said.

The possession was promised by September 7, 2019. However, a valid offer of possession was made only on June 27, 2025, he said.

Penalising the developer for this delay, the authority directed that 44.63 lakh be paid to the couple as interest. It ordered issuance of a Debt Recovery Certificate if Omaxe fails to pay within 90 days.

The authority clarified that though the 2015 agreement was executed before RERA came into force, the promoter is still liable for delay under Section 18 of the Real Estate (Regulation and Development) Act.

RERA also noted that Omaxe obtained the occupancy certificate for the project only on November 26, 2024, well after the committed date.

It also examined the builder’s increase of the super area from 1,885 sq ft to 1,975 sq ft, holding that such an increase cannot be imposed without the allottee’s prior consent.

The authority made it clear that the promoter cannot raise any financial demand on the basis of this unilateral increase.

 