Mumbai-Ahmedabad bullet train project: Major breakthrough achieved at Ghansoli tunnel

The excavation for this tunnel began back in May 2024 in three phases; the first breakthrough was achieved on July 9.

Published on: Sep 20, 2025 03:13 PM IST
Advertisement

The Mumbai Ahmedabad bullet train project saw a major breakthrough on the 4.88 km-long tunnel between Shilphata and Ghansoli. The breakthrough was achieved on Saturday morning, the National High Speed Rail Corporation Limited (NHSRCL) said.

Union Railway Minister Ashwini Vaishnaw was present at the Ghansoli shaft when this breakthrough was achieved by way of a controlled blast (Bloomberg/Representational Image)
Union Railway Minister Ashwini Vaishnaw was present at the Ghansoli shaft when this breakthrough was achieved by way of a controlled blast (Bloomberg/Representational Image)

Union railway minister Ashwini Vaishnaw was present at the Ghansoli shaft when this breakthrough was achieved by way of a controlled blast, news agency PTI reported. The tunnel is a part of the 21-km underground stretch between the Bandra-Kurla Complex (BKC) and Shilphata, including a seven-km segment beneath Thane Creek. It was excavated using the New Austrian Tunnel Method (NATM).

With this latest development, the bullet train tunnel now connects the Savali shaft to the tunnel portal at Shilpata, linking it to the viaduct portion of the Mumbai-Ahmedabad High Speed Rail (MAHSR) project, the NHSRCL stated in a release.

Also read:₹15L for dumping debris on open plot"> PMC fines Metro line 3 project 15L for dumping debris on open plot

The next phase of the project will involve waterproofing, lining and finishing the tunnel as well as equipment installation. The remaining 16 km of tunnelling will be executed using tunnel boring machines (TBMs).

The NATM tunnel has an internal width of 12.6 metres and was constructed using drilling, blasting, survey works, and support systems under challenging geological conditions.

Once completed, the tunnel will be a single tube with a 13.1-metre diameter structure accommodating twin tracks for both up and down lines.

Also read: Bullet train on Mumbai-Ahmedabad to cut travel time to just 2 hrs soon: Vaishnaw

It will also feature comprehensive safety measures, including settlement markers, piezometers, inclinometers, strain gauges and restricted site access. There will also be accommodations for pumping fresh air for workers inside the tunnel.

The 508 km-long Mumbai-Ahmedabad high-speed rail corridor is India's first bullet train project. According to the NHSRCL, work has been completed on 321 km of viaduct, 398 km of pier, along with 17 river bridges, nine steel bridges, and the installation of over four lakh noise barriers across 206 km.

The track bed has been completed along 206 kilometres, and over 2,000 overhead equipment masts have been installed, covering 48 kilometres of the mainline viaduct, the statement said.

 
ABOUT THE AUTHOR
HT News Desk

Follow the latest breaking news, major developments and agenda-setting stories from India and around the world with the newsdesk at Hindustan Times. Operating round the clock, the desk brings together experienced editors, reporters and correspondents to deliver fast, accurate and contextual reporting across subjects that influence public policy, governance, business, society and international affairs. The HT News Desk covers politics, elections, government policies, the economy, business and markets, science and technology, the environment, law and order, infrastructure, education, climate issues and geopolitics, while closely tracking developments across states, institutions and global capitals. The team also leads coverage of major breaking news events, policy announcements, court proceedings, natural disasters, public emergencies and significant international developments. Reports published by the newsdesk are based on information gathered from reporters on the ground, official statements, government agencies, court records, regulatory filings, recognised institutions and other authoritative sources. Stories undergo editorial scrutiny and verification processes to ensure accuracy, fairness and relevance, and are updated as events evolve and additional information becomes available. Whether covering a key political decision in New Delhi, an economic policy shift affecting millions, a landmark court ruling or a major global event, the HT News Desk aims to provide readers with reliable, fact-based journalism that delivers not only the latest developments but also the context and analysis needed to understand their wider implications.

Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe