Dam issue: Govt admits norms not followed

Maheshwar is one of the 30 major dams being built on the Narmada. The NBA says it will submerge 61 villages and produce electricity.

Published on: Jun 13, 2006 07:41 PM IST
None | By , New Delhi
Prefer HTon Google
Advertisement

Confirming a Narmada Bachao Andolan (NBA) claim, the Environment and Forest Ministry on Tuesday admitted that the work on the Rs 2,400 crore Maheshwar Hydroelectric Project at Mandleshwar in Madhya Pradesh has been suspended for non-compliance with environmental clearance conditions.

HT Image
HT Image

The Narmada Bachao Andolan had on Monday said that the action was taken after it served a legal notice on the Ministry taking objection to resumption of the work without framing comprehensive resettlement and rehabilitation (R and R) programme.

"However, the project was not part of the Narmada Complex, but a separate work on a tributary of Narmada," Secretary Environment, Pradipto Ghosh said.

It is being executed by a private party and has nothing to do with the Narmada projects, he said.

"The government took this decision after receiving representations that environmental conditions relating to relief and rehabilitation were not being fulfilled and sending its officers to verify the complaints," he said.

The NBA had last month held a protest in New Delhi after which its delegation met an additional secretary in the Ministry of Environment, demanding that environmental clearance given for the project be revoked, as agricultural lands shown available for R and R were "imaginary and non-existent."

Now on June 9, the NBA said, MEF Joint Secretary R Chandramohan issued a directive to Madhya Pradesh Chief Secretary observing that the construction work was started in violation of the conditions stipulated in the environmental clearance granted on May 1, 2001.

"The work will remain suspended till a comprehensive resettlement and rehabilitation plan is submitted by the project authorities and the same is found to be implementable by the monitoring committee after its second site meeting," the order said.

Maheshwar is one of the 30 major dams being built on the Narmada. The NBA says it will submerge 61 villages and produce electricity at prohibitively high cost on account of a five-fold increase in project cost over the last 15 years. It claims corruption and wastage of public money on the project.

In all, the NBA has been challenging the government's record on the R and R front and organising protests in the submergence zones of the Sardar Sarovar Project in Gujarat, besides the Maheshwar, Indira Sagar, Man and Veda dams in Madhya Pradesh.

 
Check India news real-time updates, latest news on Hindustan Times and more across India.
Check India news real-time updates, latest news on Hindustan Times and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe