Delhi-Noida road bottlenecks to widen

The connectivity between Delhi and Noida will get better in a month's time.

Updated on: Oct 23, 2010 12:10 AM IST
Hindustan Times | By , Noida
Prefer HTon Google
Advertisement

The connectivity between Delhi and Noida will get better in a month's time. After a survey on vehicular pressure, the work has started to expand three points at Sector 8, Jhundpura and Kondli in Noida to facilitate smooth and greater vehicular flow.

HT Image
HT Image

The three narrow points — connecting Noida to East Delhi — have a daily pressure of 70,000 vehicles. Their expansion will ease traffic snarls on the four existing full-fledged links — NH-24, Mayur Vihar, Kalindi Kunj and DND Flyway.

Despite the Metro service, connectivity between the two cities has been a problem. The Sector 8 point is burdened by vehicular pressure from Vasundhara Enclave and Mayur Vihar (both in Delhi). Jhundpura receives traffic from Delhi via Ghazipur. Vehicles coming from Mayur Vihar Phase-III also enter Noida via Kondli. The last two points lead to Sector 11 in Noida, causing traffic snarls during peak hours.

Currently, DND Flyway takes Noida traffic to Ring Road in minutes and has a daily pressure of 2.5 lakh vehicles. Kalindi Kunj bridge connects Noida and Ghaziabad to Delhi and Faridabad with a daily pressure of 1.25 lakh vehicles.

Besides, the Noida authority has plans to provide an alternative to DND Flyway. "There are some legal hurdles. We have our surveys done. Hopefully, work on a six-lane link parallel to Kalindi Kunj Yamuna Bridge will start within a year," said NP Singh, deputy CEO of Noida authority. "More coordination is required between the governments of Delhi and UP.

There have been several rounds of talks for providing taxi services across Delhi and NCR and I am hopeful," he added.

Under a concession agreement between Noida Toll Bridge Company Limited and Noida authority, there is a clause that Noida will not build a competing facility for a period of 10 years. The agreement was signed in November 1997. DND Flyway became operational in February 2001. By February 2011, the ten-year period will expire and there will be no obstruction for Noida to build another bridge.

People who commute via Kalindi Kunj Yamuna Bridge have been facing traffic jams everyday.

This bridge was built in the eighties and the main purpose was to check the flow of river to prevent floods and link Noida with Mathura road. As it is just a 2-lane link on one side it cannot cope with the present volume of traffic.

 
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk Hunger Strike LIVE and more across India.
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk Hunger Strike LIVE and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe