High mast installation hangs in balance!

TALL CLAIMS made by State Government to illuminate the entire city as well the Ardha Kumbh mela area seem to be on paper only while about 50 days are lefts for the commencement of Ardh Kumbh Mela-2007.

Published on: Nov 14, 2006 12:07 AM IST
None | By , Allahabad
Prefer HTon Google
Advertisement

TALL CLAIMS made by State Government to illuminate the entire city as well the Ardha Kumbh mela area seem to be on paper only while about 50 days are lefts for the commencement of Ardh Kumbh Mela-2007.

HT Image
HT Image

It may be mentioned that the administration had decided to install 65 high masts at cost of Rs 3.50 crore in view of the Ardh Kumbh Mela. However this seem to be in jeopardy following differences between a minister and the officials of the department concerned.

Earlier this work was supposed to be carried out jointly by Nagar Nigam, Allahabad Development Authority and DUDA but later it was handed over to the UPPCL which invited tenders.

Reputed companies like Philips, Crompton, Bajaj and Surya applied for it. Being the lowest rate, Surya's tender was approved but the State Housing and Urban Development Minister, Azam Khan during his review of mela work on October 10 reportedly took strong exception to it and ordered the officials to allot the work either to Philips or to Havells. As result the entire plan of installation of high masts seems to have been derailed. However the Ardh Kumbh Mela Adhikari Pragyan Ram Mishra said he had ample time to install the high masts.

 
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe