The Himachal Pradesh high court has stayed the de-allocation of a coal block in West Bengal to Himachal EMTA Power Ltd (HEPL) by the union coal ministry, an official said here on Saturday.

Updated on: Dec 01, 2012 04:53 PM IST
Advertisement

The Himachal Pradesh high court has stayed the de-allocation of a coal block in West Bengal to Himachal EMTA Power Ltd (HEPL) by the union coal ministry, an official said here on Saturday.

HT Image
HT Image

Hearing HEPL's petition, a division bench of justice RB Misra and justice Surinder Singh on Friday stayed the order and asked the coal ministry to its file response within four weeks.

It has listed the matter for next hearing Jan 9.

HEPL is a joint venture between the state-owned Himachal Pradesh Power Corporation Limited (HPPCL) and Eastern Minerals and Trading Agency (EMTA) for setting up a 500 MW pit-head coal-based thermal power plant at Raniganj in West Bengal.

Acting on the recommendation of the Inter-Ministerial Group (IMG) on coal, the coal ministry on November 23 de-allocated the Gourangdih ABC coal block allocated jointly to HEPL and JSW Steel on the ground that they had failed to develop it.

It also decided to deduct 50 percent of their bank guarantee, which amounted to Rs 6.67 crore.

State government officials said mining was not initiated as more than 50 percent of the coal block area was thickly populated, and mining was not possible in such places.

"We had been demanding allotment of an alternative block in its place," an official said.

 
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
Follow India news real-time updates and the latest news covered on Hindustan Times, featuring today's critical updates on Sonam Wangchuk LIVE and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe