Two more fast breeder reactors of 500 MWe capacity each would be set up at Kalpakkam, Tamil Nadu, by 2020, a top official of the Indira Gandhi Centre for Atomic Research said on Tuesday.

Updated on: Jan 26, 2010 10:06 PM IST
PTI | By , Kalpakkam (TN)
Prefer HTon Google
Advertisement

Two more fast breeder reactors of 500 MWe capacity each would be set up at Kalpakkam, Tamil Nadu, by 2020, a top official of the Indira Gandhi Centre for Atomic Research (IGCAR) said on Tuesday.

HT Image
HT Image

"In addition to the prototype Fast Breeder Reactor (FBR), work on which is nearing completion, we have planned to construct two more reactors of this kind," IGCAR Director Dr Baldev Raj told reporters here.

He said the work on the two reactors was expected to start by 2014.

On the ongoing work on the Rs 3,500-crore first FBR, Raj said the physical and civil construction was almost complete and it would be commissioned by October 2011.

The safety vessel and main vessel had already been placed in the reactor vault while the inner vessel would be installed before the reactor was closed, he said.

Other works, including primary piping and electrical, would be completed very soon, Raj said.

The testing of indigenously developed fission chamber would be carried out for three months from February end.

On cost over run, he said the increase in the prices of steel and cement would push up the cost by 15-20 per cent.

On possible competition by China in FBR technology, he said country was trying to buy two reactors from Russia.

In future, IGCAR would go in for 1000 mw FBRs, the Director added.

 
Check India news real-time updates, latest news on Hindustan Times and more across India.
Check India news real-time updates, latest news on Hindustan Times and more across India.
SHARE THIS ARTICLE ON
Hindustantimes wants to start sending you push notifications. Click allow to subscribe