MoEF gets three weeks to decide on Lavasa project

The Bombay high court on Friday gave the Ministry of Environment and Forests (MoEF) one last opportunity to pass the final order on granting post-facto environmental clearance (EC) to the Lavasa Corporation Ltd., for the construction of their hill station project in Pune district.

Updated on: Sep 24, 2011 01:05 AM IST
Hindustan Times | By , Mumbai
Prefer HTon Google
Advertisement

The Bombay high court on Friday gave the Ministry of Environment and Forests (MoEF) one last opportunity to pass the final order on granting post-facto environmental clearance (EC) to the Lavasa Corporation Ltd., for the construction of their hill station project in Pune district.

HT Image
HT Image

The division bench of justice DD Sinha and justice VK Tahilramani has given MoEF three weeks to pass the final order. “Considering the gravity and public interest of the

matter, we make it clear that the time granted today is the last chance given to the Union ministry.”

“If the ministry fails to pass an order within three weeks, the court shall hear and decide Lavasa’s petition on deemed clearance, based on merits,” the judges said.

The court was hearing a petition filed by the Lavasa Corporation, challenging the MoEF order issued on January 17, declaring that the hill station project was taken up without obtaining the mandatory EC.

On May 31, however, the expert appraisal committee of the ministry recommended post-facto EC for the first phase of the hill station.

 